Solar power plant · El Paso, CO
Clear Spring Ranch PV Project
Clear Spring Ranch PV Project is a 10 MW solar power plant in El Paso County, Colorado, operated by Madison Energy Investments LLC. Its oldest generator still running came online in 2016. In 2025 it generated 17 GWh, about what 2,200 average Colorado homes use in a year.
Clear Spring Ranch PV Project in context
Among the 185 solar plants in Colorado in the EIA's inventory, it is the 30th largest, about 0.3% of the state's 3.8 GW of solar capacity.
El Paso County has 17 power plants of 1 MW or more with 2.0 GW in all; Clear Spring Ranch PV Project is 1% of that and the 4th largest of 7 solar plants there.
Its capacity factor of 20% in 2025 is close to the 20% typical for solar plants across the US.
The average electricity customer in El Paso County goes 1.0 hours a year without power, the 38th most of 39 counties in Colorado. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Clear Spring Ranch PV Project (outlined) and other plants in El Paso County, shaded. 38.602, -104.695.
Plant facts
- Operator
- Madison Energy Investments LLC
- Sector
- IPP Non-CHP
- Grid operator
- WACM
- County
- El Paso County, CO
- EIA plant ID
- 60511
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| PV1 | Solar Photovoltaic | 10 MW | 2016 | – |
Questions
Clear Spring Ranch PV Project, answered
How much power does Clear Spring Ranch PV Project produce?
Clear Spring Ranch PV Project has 10 MW of capacity from one generator. In 2025 it generated 17 GWh, 20% of the most it could have made running flat out all year (its capacity factor).
How many homes does Clear Spring Ranch PV Project power?
Its 2025 output of 17 GWh equals the yearly electricity use of about 2,200 average Colorado homes (658 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Clear Spring Ranch PV Project?
Clear Spring Ranch PV Project is in El Paso County, Colorado, at about 38.602°, -104.695°. It is one of 17 power plants of 1 MW or more in the county. The average electricity customer in El Paso County goes 1.0 hours a year without power, the 38th most of 39 counties in Colorado. The county's page has the full outage record.
Who operates Clear Spring Ranch PV Project?
It is operated by Madison Energy Investments LLC (EIA sector: IPP Non-CHP), and it feeds WAPA Rocky Mountain.
When did Clear Spring Ranch PV Project open?
Its oldest generator still running came online in 2016.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Colorado home's 658 kWh a month in 2025. Methodology.