Solar power plant · El Paso, CO

Pike Solar Hybrid

Pike Solar Hybrid is a 175 MW solar power plant in El Paso County, Colorado, operated by Deriva Energy. Its oldest generator still running came online in 2023. In 2025 it generated 446 GWh, about what 57,000 average Colorado homes use in a year.

Capacity175 MWNameplate, September 2026
Generated446 GWhIn 2025
Capacity factor29%Share of the most it could make, 2025
Generators1Oldest from 2023

Pike Solar Hybrid in context

Among the 185 solar plants in Colorado in the EIA's inventory, it is the 7th largest, about 4.6% of the state's 3.8 GW of solar capacity.

El Paso County has 17 power plants of 1 MW or more with 2.0 GW in all; Pike Solar Hybrid is 9% of that and the largest of 7 solar plants there.

Its capacity factor of 29% in 2025 is higher than the 20% typical for solar plants across the US.

The average electricity customer in El Paso County goes 1.0 hours a year without power, the 38th most of 39 counties in Colorado. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

0100200300400500202320242025GWh 446
0100200300400500202320242025446

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Pike Solar Hybrid (outlined) and other plants in El Paso County, shaded. 38.622, -104.581.

Plant facts

Operator
Deriva Energy
Sector
IPP Non-CHP
Grid operator
PSCO
County
El Paso County, CO
EIA plant ID
64212
Where Colorado's power comes from → Colorado power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
CO465 Solar Photovoltaic 175 MW 2023 –

Questions

Pike Solar Hybrid, answered

How much power does Pike Solar Hybrid produce?

Pike Solar Hybrid has 175 MW of capacity from one generator. In 2025 it generated 446 GWh, 29% of the most it could have made running flat out all year (its capacity factor).

How many homes does Pike Solar Hybrid power?

Its 2025 output of 446 GWh equals the yearly electricity use of about 57,000 average Colorado homes (658 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Pike Solar Hybrid?

Pike Solar Hybrid is in El Paso County, Colorado, at about 38.622°, -104.581°. It is one of 17 power plants of 1 MW or more in the county. The average electricity customer in El Paso County goes 1.0 hours a year without power, the 38th most of 39 counties in Colorado. The county's page has the full outage record.

Who operates Pike Solar Hybrid?

It is operated by Deriva Energy (EIA sector: IPP Non-CHP), and it feeds Public Service Company of Colorado.

When did Pike Solar Hybrid open?

Its oldest generator still running came online in 2023.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2023–2025). Homes equivalent uses the average Colorado home's 658 kWh a month in 2025. Methodology.