Solar power plant · El Paso, CO
Pike Solar Hybrid
Pike Solar Hybrid is a 175 MW solar power plant in El Paso County, Colorado, operated by Deriva Energy. Its oldest generator still running came online in 2023. In 2025 it generated 446 GWh, about what 57,000 average Colorado homes use in a year.
Pike Solar Hybrid in context
Among the 185 solar plants in Colorado in the EIA's inventory, it is the 7th largest, about 4.6% of the state's 3.8 GW of solar capacity.
El Paso County has 17 power plants of 1 MW or more with 2.0 GW in all; Pike Solar Hybrid is 9% of that and the largest of 7 solar plants there.
Its capacity factor of 29% in 2025 is higher than the 20% typical for solar plants across the US.
The average electricity customer in El Paso County goes 1.0 hours a year without power, the 38th most of 39 counties in Colorado. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Pike Solar Hybrid (outlined) and other plants in El Paso County, shaded. 38.622, -104.581.
Plant facts
- Operator
- Deriva Energy
- Sector
- IPP Non-CHP
- Grid operator
- PSCO
- County
- El Paso County, CO
- EIA plant ID
- 64212
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| CO465 | Solar Photovoltaic | 175 MW | 2023 | – |
Questions
Pike Solar Hybrid, answered
How much power does Pike Solar Hybrid produce?
Pike Solar Hybrid has 175 MW of capacity from one generator. In 2025 it generated 446 GWh, 29% of the most it could have made running flat out all year (its capacity factor).
How many homes does Pike Solar Hybrid power?
Its 2025 output of 446 GWh equals the yearly electricity use of about 57,000 average Colorado homes (658 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Pike Solar Hybrid?
Pike Solar Hybrid is in El Paso County, Colorado, at about 38.622°, -104.581°. It is one of 17 power plants of 1 MW or more in the county. The average electricity customer in El Paso County goes 1.0 hours a year without power, the 38th most of 39 counties in Colorado. The county's page has the full outage record.
Who operates Pike Solar Hybrid?
It is operated by Deriva Energy (EIA sector: IPP Non-CHP), and it feeds Public Service Company of Colorado.
When did Pike Solar Hybrid open?
Its oldest generator still running came online in 2023.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2023–2025). Homes equivalent uses the average Colorado home's 658 kWh a month in 2025. Methodology.