Natural gas power plant · Cleveland, NC
Cleveland Cnty Generating Facility
Cleveland Cnty Generating Facility is a 736 MW natural gas power plant in Cleveland County, North Carolina, operated by Southern Power Co. Its oldest generator still running came online in 2012. In 2025 it generated 986 GWh, about what 79,000 average North Carolina homes use in a year.
Cleveland Cnty Generating Facility in context
Among the 22 natural gas plants in North Carolina in the EIA's inventory, it is the 12th largest, about 3.6% of the state's 20 GW of natural gas capacity.
Cleveland County has 30 power plants of 1 MW or more with 3.0 GW in all; Cleveland Cnty Generating Facility is 25% of that and the 2nd largest of 3 natural gas plants there.
Its capacity factor of 15% in 2025 is lower than the 23% typical for natural gas plants across the US.
The average electricity customer in Cleveland County goes 10 hours a year without power, the 45th most of 100 counties in North Carolina. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Cleveland Cnty Generating Facility (outlined) and other plants in Cleveland County, shaded. 35.171, -81.417.
Plant facts
- Operator
- Southern Power Co
- Sector
- IPP Non-CHP
- Grid operator
- DUK
- County
- Cleveland County, NC
- EIA plant ID
- 57029
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Natural Gas Fired Combustion Turbine | 184 MW | 2012 | – |
| 2 | Natural Gas Fired Combustion Turbine | 184 MW | 2012 | – |
| 3 | Natural Gas Fired Combustion Turbine | 184 MW | 2012 | – |
| 4 | Natural Gas Fired Combustion Turbine | 184 MW | 2012 | – |
Nearby
Other plants in Cleveland County
Questions
Cleveland Cnty Generating Facility, answered
How much power does Cleveland Cnty Generating Facility produce?
Cleveland Cnty Generating Facility has 736 MW of capacity from 4 generators. In 2025 it generated 986 GWh, 15% of the most it could have made running flat out all year (its capacity factor).
How many homes does Cleveland Cnty Generating Facility power?
Its 2025 output of 986 GWh equals the yearly electricity use of about 79,000 average North Carolina homes (1,044 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Cleveland Cnty Generating Facility?
Cleveland Cnty Generating Facility is in Cleveland County, North Carolina, at about 35.171°, -81.417°. It is one of 30 power plants of 1 MW or more in the county. The average electricity customer in Cleveland County goes 10 hours a year without power, the 45th most of 100 counties in North Carolina. The county's page has the full outage record.
Who operates Cleveland Cnty Generating Facility?
It is operated by Southern Power Co (EIA sector: IPP Non-CHP), and it feeds Duke Energy Carolinas.
When did Cleveland Cnty Generating Facility open?
Its oldest generator still running came online in 2012.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average North Carolina home's 1,044 kWh a month in 2025. Methodology.