Wind power plant · Umatilla, OR
Combine Hills I
Combine Hills I is a 43 MW wind power plant in Umatilla County, Oregon, operated by Eurus Combine Hills I LLC. Its oldest generator still running came online in 2003. In 2025 it generated 61 GWh, about what 5,900 average Oregon homes use in a year.
Combine Hills I in context
Among the 50 wind plants in Oregon in the EIA's inventory, it is the 25th largest, about 1.0% of the state's 4.3 GW of wind capacity.
Umatilla County has 17 power plants of 1 MW or more with 2.7 GW in all; Combine Hills I is 2% of that and the 4th largest of 11 wind plants there.
Its capacity factor of 16% in 2025 is lower than the 32% typical for wind plants across the US.
The average electricity customer in Umatilla County goes 3.9 hours a year without power, the 26th most of 32 counties in Oregon. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Combine Hills I (outlined) and other plants in Umatilla County, shaded. 45.943, -118.591.
Plant facts
- Operator
- Eurus Combine Hills I LLC
- Sector
- IPP Non-CHP
- Grid operator
- PACW
- County
- Umatilla County, OR
- EIA plant ID
- 56195
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 001 | Onshore Wind Turbine | 43 MW | 2003 | – |
Questions
Combine Hills I, answered
How much power does Combine Hills I produce?
Combine Hills I has 43 MW of capacity from one generator. In 2025 it generated 61 GWh, 16% of the most it could have made running flat out all year (its capacity factor).
How many homes does Combine Hills I power?
Its 2025 output of 61 GWh equals the yearly electricity use of about 5,900 average Oregon homes (866 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Combine Hills I?
Combine Hills I is in Umatilla County, Oregon, at about 45.943°, -118.591°. It is one of 17 power plants of 1 MW or more in the county. The average electricity customer in Umatilla County goes 3.9 hours a year without power, the 26th most of 32 counties in Oregon. The county's page has the full outage record.
Who operates Combine Hills I?
It is operated by Eurus Combine Hills I LLC (EIA sector: IPP Non-CHP), and it feeds PacifiCorp West.
When did Combine Hills I open?
Its oldest generator still running came online in 2003.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Oregon home's 866 kWh a month in 2025. Methodology.