Wind power plant · Umatilla, OR

FPL Energy Vansycle LLC (OR)

FPL Energy Vansycle LLC (OR) is a 123 MW wind power plant in Umatilla County, Oregon, operated by FPL Energy Vansycle LLC. Its oldest generator still running came online in 2001. In 2025 it generated 225 GWh, about what 22,000 average Oregon homes use in a year.

Capacity123 MWNameplate, September 2026
Generated225 GWhIn 2025
Capacity factor21%Share of the most it could make, 2025
Generators1Oldest from 2001

FPL Energy Vansycle LLC (OR) in context

Among the 50 wind plants in Oregon in the EIA's inventory, it is the 11th largest, about 2.9% of the state's 4.3 GW of wind capacity.

Umatilla County has 17 power plants of 1 MW or more with 2.7 GW in all; FPL Energy Vansycle LLC (OR) is 5% of that and the largest of 11 wind plants there.

Its capacity factor of 21% in 2025 is lower than the 32% typical for wind plants across the US.

The average electricity customer in Umatilla County goes 3.9 hours a year without power, the 26th most of 32 counties in Oregon. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

010020030040020182019202020212022202320242025GWh 225
01002003004002019202120232025225

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

FPL Energy Vansycle LLC (OR) (outlined) and other plants in Umatilla County, shaded. 46.013, -118.816.

Plant facts

Operator
FPL Energy Vansycle LLC
Sector
IPP Non-CHP
Grid operator
BPAT
County
Umatilla County, OR
EIA plant ID
55989
Where Oregon's power comes from → Oregon power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
V-47 Onshore Wind Turbine 123 MW 2001 –

Questions

FPL Energy Vansycle LLC (OR), answered

How much power does FPL Energy Vansycle LLC (OR) produce?

FPL Energy Vansycle LLC (OR) has 123 MW of capacity from one generator. In 2025 it generated 225 GWh, 21% of the most it could have made running flat out all year (its capacity factor).

How many homes does FPL Energy Vansycle LLC (OR) power?

Its 2025 output of 225 GWh equals the yearly electricity use of about 22,000 average Oregon homes (866 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is FPL Energy Vansycle LLC (OR)?

FPL Energy Vansycle LLC (OR) is in Umatilla County, Oregon, at about 46.013°, -118.816°. It is one of 17 power plants of 1 MW or more in the county. The average electricity customer in Umatilla County goes 3.9 hours a year without power, the 26th most of 32 counties in Oregon. The county's page has the full outage record.

Who operates FPL Energy Vansycle LLC (OR)?

It is operated by FPL Energy Vansycle LLC (EIA sector: IPP Non-CHP), and it feeds the Bonneville Power Administration.

When did FPL Energy Vansycle LLC (OR) open?

Its oldest generator still running came online in 2001.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Oregon home's 866 kWh a month in 2025. Methodology.