Wind power plant · Dickey, ND

Foxtail Wind, LLC

Foxtail Wind, LLC is a 150 MW wind power plant in Dickey County, North Dakota, operated by Foxtail Wind, LLC. Its oldest generator still running came online in 2020. In 2025 it generated 623 GWh, about what 49,000 average North Dakota homes use in a year.

Capacity150 MWNameplate, September 2026
Generated623 GWhIn 2025
Capacity factor47%Share of the most it could make, 2025
Generators1Oldest from 2020

Foxtail Wind, LLC in context

Among the 42 wind plants in North Dakota in the EIA's inventory, it is the 16th largest, about 3.0% of the state's 5.0 GW of wind capacity.

Dickey County has 2 power plants of 1 MW or more with 330 MW in all; Foxtail Wind, LLC is 45% of that and the 2nd largest of 2 wind plants there.

Its capacity factor of 47% in 2025 is higher than the 32% typical for wind plants across the US.

The average electricity customer in Dickey County goes 9.3 hours a year without power, the 6th most of 13 counties in North Dakota. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

0200400600800202020212022202320242025GWh 623
0200400600800202020212022202320242025623

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Foxtail Wind, LLC (outlined) and other plants in Dickey County, shaded. 46.098, -98.880.

Plant facts

Operator
Foxtail Wind, LLC
Sector
Electric Utility
Grid operator
MISO
County
Dickey County, ND
EIA plant ID
61747
Where North Dakota's power comes from → North Dakota power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
1 Onshore Wind Turbine 150 MW 2020 –

Nearby

Other plants in Dickey County

Questions

Foxtail Wind, LLC, answered

How much power does Foxtail Wind, LLC produce?

Foxtail Wind, LLC has 150 MW of capacity from one generator. In 2025 it generated 623 GWh, 47% of the most it could have made running flat out all year (its capacity factor).

How many homes does Foxtail Wind, LLC power?

Its 2025 output of 623 GWh equals the yearly electricity use of about 49,000 average North Dakota homes (1,070 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Foxtail Wind, LLC?

Foxtail Wind, LLC is in Dickey County, North Dakota, at about 46.098°, -98.880°. It is one of 2 power plants of 1 MW or more in the county. The average electricity customer in Dickey County goes 9.3 hours a year without power, the 6th most of 13 counties in North Dakota. The county's page has the full outage record.

Who operates Foxtail Wind, LLC?

It is operated by Foxtail Wind, LLC (EIA sector: Electric Utility), and it feeds MISO.

When did Foxtail Wind, LLC open?

Its oldest generator still running came online in 2020.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2020–2025). Homes equivalent uses the average North Dakota home's 1,070 kWh a month in 2025. Methodology.