Natural gas power plant · Kings, CA
Henrietta Peaker
Henrietta Peaker is a 98 MW natural gas power plant in Kings County, California, operated by MRP San Joaquin Energy LLC.. Its oldest generator still running came online in 2002. In 2025 it generated 3.8 GWh, about what 641 average California homes use in a year.
Henrietta Peaker in context
Among the 304 natural gas plants in California in the EIA's inventory, it is the 81st largest, about 0.2% of the state's 41 GW of natural gas capacity.
Kings County has 52 power plants of 1 MW or more with 2.8 GW in all; Henrietta Peaker is 3% of that and the largest of 2 natural gas plants there.
Its capacity factor of 0% in 2025 is lower than the 23% typical for natural gas plants across the US.
The average electricity customer in Kings County goes 2.9 hours a year without power, the 51st most of 56 counties in California. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Henrietta Peaker (outlined) and other plants in Kings County, shaded. 36.240, -119.904.
Plant facts
- Operator
- MRP San Joaquin Energy LLC.
- Sector
- IPP Non-CHP
- Grid operator
- CISO
- County
- Kings County, CA
- EIA plant ID
- 55807
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| HPP1 | Natural Gas Fired Combustion Turbine | 49 MW | 2002 | – |
| HPP2 | Natural Gas Fired Combustion Turbine | 49 MW | 2002 | – |
Questions
Henrietta Peaker, answered
How much power does Henrietta Peaker produce?
Henrietta Peaker has 98 MW of capacity from 2 generators. In 2025 it generated 3.8 GWh, 0% of the most it could have made running flat out all year (its capacity factor).
How many homes does Henrietta Peaker power?
Its 2025 output of 3.8 GWh equals the yearly electricity use of about 641 average California homes (494 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Henrietta Peaker?
Henrietta Peaker is in Kings County, California, at about 36.240°, -119.904°. It is one of 52 power plants of 1 MW or more in the county. The average electricity customer in Kings County goes 2.9 hours a year without power, the 51st most of 56 counties in California. The county's page has the full outage record.
Who operates Henrietta Peaker?
It is operated by MRP San Joaquin Energy LLC. (EIA sector: IPP Non-CHP), and it feeds the California ISO.
When did Henrietta Peaker open?
Its oldest generator still running came online in 2002.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average California home's 494 kWh a month in 2025. Methodology.