Hydro power plant · Cumberland, ME
Hiram
Hiram is a 11 MW hydro power plant in Cumberland County, Maine, operated by Brookfield White Pine Hydro LLC. Its oldest generator still running came online in 1917. In 2025 it generated 31 GWh, about what 4,900 average Maine homes use in a year.
Hiram in context
Among the 48 hydro plants in Maine in the EIA's inventory, it is the 16th largest, about 1.5% of the state's 700 MW of hydro capacity.
Cumberland County has 23 power plants of 1 MW or more with 1.8 GW in all; Hiram is 1% of that and the 2nd largest of 3 hydro plants there.
Its capacity factor of 34% in 2025 is close to the 34% typical for hydro plants across the US.
The average electricity customer in Cumberland County goes 12 hours a year without power, the 15th most of 16 counties in Maine. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Hiram (outlined) and other plants in Cumberland County, shaded. 43.852, -70.797.
Plant facts
- Operator
- Brookfield White Pine Hydro LLC
- Sector
- IPP Non-CHP
- Grid operator
- ISNE
- County
- Cumberland County, ME
- EIA plant ID
- 1493
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 2 | Conventional Hydroelectric | 8.1 MW | 1985 | – |
| 1 | Conventional Hydroelectric | 2.4 MW | 1917 | – |
Nearby
Other plants in Cumberland County
Questions
Hiram, answered
How much power does Hiram produce?
Hiram has 11 MW of capacity from 2 generators. In 2025 it generated 31 GWh, 34% of the most it could have made running flat out all year (its capacity factor).
How many homes does Hiram power?
Its 2025 output of 31 GWh equals the yearly electricity use of about 4,900 average Maine homes (533 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Hiram?
Hiram is in Cumberland County, Maine, at about 43.852°, -70.797°. It is one of 23 power plants of 1 MW or more in the county. The average electricity customer in Cumberland County goes 12 hours a year without power, the 15th most of 16 counties in Maine. The county's page has the full outage record.
Who operates Hiram?
It is operated by Brookfield White Pine Hydro LLC (EIA sector: IPP Non-CHP), and it feeds ISO New England.
When did Hiram open?
Its oldest generator still running came online in 1917.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Maine home's 533 kWh a month in 2025. Methodology.