Oil power plant · Cumberland, ME

William F Wyman Hybrid

William F Wyman Hybrid is a 863 MW oil power plant in Cumberland County, Maine, operated by FPL Energy Wyman LLC. Its oldest generator still running came online in 1957. In 2025 it generated 138 GWh, about what 22,000 average Maine homes use in a year.

Capacity863 MWNameplate, September 2026
Generated138 GWhIn 2025
Capacity factor2%Share of the most it could make, 2025
Generators5Oldest from 1957

William F Wyman Hybrid in context

Among the 19 other-fuel plants in Maine in the EIA's inventory, it is the largest, about 57% of the state's 1.5 GW of other-fuel capacity.

Cumberland County has 23 power plants of 1 MW or more with 1.8 GW in all; William F Wyman Hybrid is 48% of that and the largest of 4 oil plants there.

Its capacity factor of 2% in 2025 is lower than the 25% typical for oil plants across the US.

The average electricity customer in Cumberland County goes 12 hours a year without power, the 15th most of 16 counties in Maine. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

010020030020182019202020212022202320242025GWh 138
01002003002019202120232025138

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

William F Wyman Hybrid (outlined) and other plants in Cumberland County, shaded. 43.751, -70.157.

Plant facts

Operator
FPL Energy Wyman LLC
Sector
IPP Non-CHP
Grid operator
ISNE
County
Cumberland County, ME
EIA plant ID
1507
  • Other846 MW98%
  • Storage17 MW1.9%
Where Maine's power comes from → Maine power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
4 Petroleum Liquids 632 MW 1978 –
3 Petroleum Liquids 114 MW 1965 –
1 Petroleum Liquids 50 MW 1957 –
2 Petroleum Liquids 50 MW 1958 –
BESS Batteries 17 MW · 11 MWh 2016 –

Questions

William F Wyman Hybrid, answered

How much power does William F Wyman Hybrid produce?

William F Wyman Hybrid has 863 MW of capacity from 5 generators. In 2025 it generated 138 GWh, 2% of the most it could have made running flat out all year (its capacity factor).

How many homes does William F Wyman Hybrid power?

Its 2025 output of 138 GWh equals the yearly electricity use of about 22,000 average Maine homes (533 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is William F Wyman Hybrid?

William F Wyman Hybrid is in Cumberland County, Maine, at about 43.751°, -70.157°. It is one of 23 power plants of 1 MW or more in the county. The average electricity customer in Cumberland County goes 12 hours a year without power, the 15th most of 16 counties in Maine. The county's page has the full outage record.

Who operates William F Wyman Hybrid?

It is operated by FPL Energy Wyman LLC (EIA sector: IPP Non-CHP), and it feeds ISO New England.

When did William F Wyman Hybrid open?

Its oldest generator still running came online in 1957.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Maine home's 533 kWh a month in 2025. Methodology.