Wind power plant · Haskell, TX

Horse Creek Wind Farm

Horse Creek Wind Farm is a 230 MW wind power plant in Haskell County, Texas, operated by Horse Creek Wind, LLC. Its oldest generator still running came online in 2016. In 2025 it generated 820 GWh, about what 62,000 average Texas homes use in a year.

Capacity230 MWNameplate, September 2026
Generated820 GWhIn 2025
Capacity factor41%Share of the most it could make, 2025
Generators1Oldest from 2016

Horse Creek Wind Farm in context

Among the 230 wind plants in Texas in the EIA's inventory, it is the 66th largest, about 0.5% of the state's 45 GW of wind capacity.

Haskell County has 8 power plants of 1 MW or more with 1.8 GW in all; Horse Creek Wind Farm is 13% of that and the 3rd largest of 4 wind plants there.

Its capacity factor of 41% in 2025 is higher than the 32% typical for wind plants across the US.

The average electricity customer in Haskell County goes 19 hours a year without power, the 44th most of 240 counties in Texas. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

02004006008001,00020182019202020212022202320242025GWh 820
02004006008001,0002019202120232025820

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Horse Creek Wind Farm (outlined) and other plants in Haskell County, shaded. 33.350, -99.540.

Plant facts

Operator
Horse Creek Wind, LLC
Sector
IPP Non-CHP
Grid operator
ERCO
County
Haskell County, TX
EIA plant ID
60339
Where Texas's power comes from → Texas power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
HCWF Onshore Wind Turbine 230 MW 2016 –

Questions

Horse Creek Wind Farm, answered

How much power does Horse Creek Wind Farm produce?

Horse Creek Wind Farm has 230 MW of capacity from one generator. In 2025 it generated 820 GWh, 41% of the most it could have made running flat out all year (its capacity factor).

How many homes does Horse Creek Wind Farm power?

Its 2025 output of 820 GWh equals the yearly electricity use of about 62,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Horse Creek Wind Farm?

Horse Creek Wind Farm is in Haskell County, Texas, at about 33.350°, -99.540°. It is one of 8 power plants of 1 MW or more in the county. The average electricity customer in Haskell County goes 19 hours a year without power, the 44th most of 240 counties in Texas. The county's page has the full outage record.

Who operates Horse Creek Wind Farm?

It is operated by Horse Creek Wind, LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.

When did Horse Creek Wind Farm open?

Its oldest generator still running came online in 2016.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.