Solar power plant · Rio Arriba, NM
Jicarilla Solar 1 LLC
Jicarilla Solar 1 LLC is a 70 MW solar power plant in Rio Arriba County, New Mexico, operated by Repsol Renewables NA. Its oldest generator still running came online in 2023. In 2025 it generated 107 GWh, about what 14,000 average New Mexico homes use in a year.
Jicarilla Solar 1 LLC in context
Among the 111 solar plants in New Mexico in the EIA's inventory, it is the 15th largest, about 1.8% of the state's 3.8 GW of solar capacity.
Rio Arriba County has 7 power plants of 1 MW or more with 338 MW in all; Jicarilla Solar 1 LLC is 21% of that and the 2nd largest of 5 solar plants there.
Its capacity factor of 17% in 2025 is lower than the 20% typical for solar plants across the US.
The average electricity customer in Rio Arriba County goes 10 hours a year without power, the 3rd most of 20 counties in New Mexico. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Jicarilla Solar 1 LLC (outlined) and other plants in Rio Arriba County, shaded. 36.317, -107.278.
Plant facts
- Operator
- Repsol Renewables NA
- Sector
- IPP Non-CHP
- Grid operator
- PNM
- County
- Rio Arriba County, NM
- EIA plant ID
- 66163
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| JICS1 | Solar Photovoltaic | 50 MW | 2023 | – |
| JICB1 | Batteries | 20 MW · 80 MWh | 2023 | – |
Nearby
Other plants in Rio Arriba County
Questions
Jicarilla Solar 1 LLC, answered
How much power does Jicarilla Solar 1 LLC produce?
Jicarilla Solar 1 LLC has 70 MW of capacity from 2 generators. In 2025 it generated 107 GWh, 17% of the most it could have made running flat out all year (its capacity factor).
How many homes does Jicarilla Solar 1 LLC power?
Its 2025 output of 107 GWh equals the yearly electricity use of about 14,000 average New Mexico homes (638 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Jicarilla Solar 1 LLC?
Jicarilla Solar 1 LLC is in Rio Arriba County, New Mexico, at about 36.317°, -107.278°. It is one of 7 power plants of 1 MW or more in the county. The average electricity customer in Rio Arriba County goes 10 hours a year without power, the 3rd most of 20 counties in New Mexico. The county's page has the full outage record.
Who operates Jicarilla Solar 1 LLC?
It is operated by Repsol Renewables NA (EIA sector: IPP Non-CHP), and it feeds balancing authority PNM.
When did Jicarilla Solar 1 LLC open?
Its oldest generator still running came online in 2023.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2023–2025). Homes equivalent uses the average New Mexico home's 638 kWh a month in 2025. Methodology.