Hydro power plant · Carbon, WY

Kortes

Kortes is a 36 MW hydro power plant in Carbon County, Wyoming, operated by U S Bureau of Reclamation. Its oldest generator still running came online in 1950. In 2025 it generated 106 GWh, about what 11,000 average Wyoming homes use in a year.

Capacity36 MWNameplate, September 2026
Generated106 GWhIn 2025
Capacity factor34%Share of the most it could make, 2025
Generators3Oldest from 1950

Kortes in context

Among the 16 hydro plants in Wyoming in the EIA's inventory, it is the 5th largest, about 12% of the state's 303 MW of hydro capacity.

Carbon County has 9 power plants of 1 MW or more with 1.8 GW in all; Kortes is 2% of that and the 2nd largest of 2 hydro plants there.

Its capacity factor of 34% in 2025 is close to the 34% typical for hydro plants across the US.

The average electricity customer in Carbon County goes 3.0 hours a year without power, the 8th most of 20 counties in Wyoming. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

05010015020020182019202020212022202320242025GWh 106
0501001502002019202120232025106

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Kortes (outlined) and other plants in Carbon County, shaded. 42.174, -106.880.

Plant facts

Operator
U S Bureau of Reclamation
Sector
Electric Utility
Grid operator
WAUW
County
Carbon County, WY
EIA plant ID
4180
Where Wyoming's power comes from → Wyoming power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
2 Conventional Hydroelectric 12 MW 1950 –
3 Conventional Hydroelectric 12 MW 1950 –
1 Conventional Hydroelectric 12 MW 1951 –

Questions

Kortes, answered

How much power does Kortes produce?

Kortes has 36 MW of capacity from 3 generators. In 2025 it generated 106 GWh, 34% of the most it could have made running flat out all year (its capacity factor).

How many homes does Kortes power?

Its 2025 output of 106 GWh equals the yearly electricity use of about 11,000 average Wyoming homes (835 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Kortes?

Kortes is in Carbon County, Wyoming, at about 42.174°, -106.880°. It is one of 9 power plants of 1 MW or more in the county. The average electricity customer in Carbon County goes 3.0 hours a year without power, the 8th most of 20 counties in Wyoming. The county's page has the full outage record.

Who operates Kortes?

It is operated by U S Bureau of Reclamation (EIA sector: Electric Utility), and it feeds balancing authority WAUW.

When did Kortes open?

Its oldest generator still running came online in 1950.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Wyoming home's 835 kWh a month in 2025. Methodology.