Storage power plant · Kings, CA

Lead BESS 1

Lead BESS 1 is a 99 MW storage power plant in Kings County, California, operated by Hanford BESS LLC. Its oldest generator still running came online in 2025.

Capacity99 MWNameplate, September 2026
Net energy-0.8 GWhIn 2025
Capacity factor–Not a full year of data
Generators1Oldest from 2025

Lead BESS 1 in context

Among the 156 storage plants in California in the EIA's inventory, it is the 42nd largest, about 0.7% of the state's 13 GW of storage capacity.

Kings County has 52 power plants of 1 MW or more with 2.8 GW in all; Lead BESS 1 is 4% of that and the largest of 5 storage plants there.

The average electricity customer in Kings County goes 2.9 hours a year without power, the 51st most of 56 counties in California. The county's page has the full outage record.

Where it is

Lead BESS 1 (outlined) and other plants in Kings County, shaded. 36.270, -119.649.

Plant facts

Operator
Hanford BESS LLC
Sector
IPP Non-CHP
Grid operator
CISO
County
Kings County, CA
EIA plant ID
66660
Where California's power comes from → California power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
HAN Batteries 99 MW · 99 MWh 2025 –

Questions

Lead BESS 1, answered

How much can Lead BESS 1 store and deliver?

Lead BESS 1 can deliver up to 99 MW and hold 99 MWh of energy, from one battery or storage system. Its net energy in 2025 was -0.8 GWh: a storage plant uses more energy charging than it returns, so the figure is usually negative.

Where is Lead BESS 1?

Lead BESS 1 is in Kings County, California, at about 36.270°, -119.649°. It is one of 52 power plants of 1 MW or more in the county. The average electricity customer in Kings County goes 2.9 hours a year without power, the 51st most of 56 counties in California. The county's page has the full outage record.

Who operates Lead BESS 1?

It is operated by Hanford BESS LLC (EIA sector: IPP Non-CHP), and it feeds the California ISO.

When did Lead BESS 1 open?

Its oldest generator still running came online in 2025.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Methodology.