Natural gas power plant · Butler, OH

Middletown Energy Center

Middletown Energy Center is a 544 MW natural gas power plant in Butler County, Ohio, operated by Ohio Power Partners, LLC. Its oldest generator still running came online in 2018. In 2025 it generated 3.1 TWh, about what 300,000 average Ohio homes use in a year.

Capacity544 MWNameplate, September 2026
Generated3.1 TWhIn 2025
Capacity factor66%Share of the most it could make, 2025
Generators2Oldest from 2018

Middletown Energy Center in context

Among the 48 natural gas plants in Ohio in the EIA's inventory, it is the 20th largest, about 2.8% of the state's 20 GW of natural gas capacity.

Butler County has 8 power plants of 1 MW or more with 2.1 GW in all; Middletown Energy Center is 26% of that and the 3rd largest of 6 natural gas plants there.

Its capacity factor of 66% in 2025 is higher than the 23% typical for natural gas plants across the US.

The average electricity customer in Butler County goes 3.5 hours a year without power, the 64th most of 88 counties in Ohio. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

01,0002,0003,0004,00020182019202020212022202320242025GWh 3,145
01,0002,0003,0004,00020192021202320253,145

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Middletown Energy Center (outlined) and other plants in Butler County, shaded. 39.465, -84.348.

Plant facts

Operator
Ohio Power Partners, LLC
Sector
IPP Non-CHP
Grid operator
PJM
County
Butler County, OH
EIA plant ID
59326
Where Ohio's power comes from → Ohio power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
MEC1 Natural Gas Fired Combined Cycle 310 MW 2018 –
MEC2 Natural Gas Fired Combined Cycle 234 MW 2018 –

Questions

Middletown Energy Center, answered

How much power does Middletown Energy Center produce?

Middletown Energy Center has 544 MW of capacity from 2 generators. In 2025 it generated 3.1 TWh, 66% of the most it could have made running flat out all year (its capacity factor).

How many homes does Middletown Energy Center power?

Its 2025 output of 3.1 TWh equals the yearly electricity use of about 300,000 average Ohio homes (874 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Middletown Energy Center?

Middletown Energy Center is in Butler County, Ohio, at about 39.465°, -84.348°. It is one of 8 power plants of 1 MW or more in the county. The average electricity customer in Butler County goes 3.5 hours a year without power, the 64th most of 88 counties in Ohio. The county's page has the full outage record.

Who operates Middletown Energy Center?

It is operated by Ohio Power Partners, LLC (EIA sector: IPP Non-CHP), and it feeds PJM Interconnection.

When did Middletown Energy Center open?

Its oldest generator still running came online in 2018.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Ohio home's 874 kWh a month in 2025. Methodology.