Solar power plant · Cameron, TX
Nebula Solar
Nebula Solar is a 135 MW solar power plant in Cameron County, Texas, operated by Rayos del Sol Solar Project, LLC. Its oldest generator still running came online in 2022. In 2025 it generated 291 GWh, about what 22,000 average Texas homes use in a year.
Nebula Solar in context
Among the 250 solar plants in Texas in the EIA's inventory, it is the 121st largest, about 0.4% of the state's 37 GW of solar capacity.
Cameron County has 23 power plants of 1 MW or more with 1.6 GW in all; Nebula Solar is 9% of that and the largest of 2 solar plants there.
Its capacity factor of 25% in 2025 is higher than the 20% typical for solar plants across the US.
The average electricity customer in Cameron County goes 4.3 hours a year without power, the 207th most of 240 counties in Texas. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Nebula Solar (outlined) and other plants in Cameron County, shaded. 26.090, -97.798.
Plant facts
- Operator
- Rayos del Sol Solar Project, LLC
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Cameron County, TX
- EIA plant ID
- 65661
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| NEB1 | Solar Photovoltaic | 135 MW | 2022 | – |
Questions
Nebula Solar, answered
How much power does Nebula Solar produce?
Nebula Solar has 135 MW of capacity from one generator. In 2025 it generated 291 GWh, 25% of the most it could have made running flat out all year (its capacity factor).
How many homes does Nebula Solar power?
Its 2025 output of 291 GWh equals the yearly electricity use of about 22,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Nebula Solar?
Nebula Solar is in Cameron County, Texas, at about 26.090°, -97.798°. It is one of 23 power plants of 1 MW or more in the county. The average electricity customer in Cameron County goes 4.3 hours a year without power, the 207th most of 240 counties in Texas. The county's page has the full outage record.
Who operates Nebula Solar?
It is operated by Rayos del Sol Solar Project, LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did Nebula Solar open?
Its oldest generator still running came online in 2022.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2022–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.