Solar power plant · Clark, NV

Nevada Solar One

Nevada Solar One is a 76 MW solar power plant in Clark County, Nevada, operated by Acciona Solar Power. Its oldest generator still running came online in 2007. In 2025 it generated 90 GWh, about what 8,600 average Nevada homes use in a year.

Capacity76 MWNameplate, September 2026
Generated90 GWhIn 2025
Capacity factor14%Share of the most it could make, 2025
Generators1Oldest from 2007

Nevada Solar One in context

Among the 58 solar plants in Nevada in the EIA's inventory, it is the 26th largest, about 1.2% of the state's 6.2 GW of solar capacity.

Clark County has 64 power plants of 1 MW or more with 14 GW in all; Nevada Solar One is 1% of that and the 20th largest of 45 solar plants there.

Its capacity factor of 14% in 2025 is lower than the 20% typical for solar plants across the US.

The average electricity customer in Clark County goes 1.2 hours a year without power, the 12th most of 12 counties in Nevada. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

05010015020182019202020212022202320242025GWh 90
050100150201920212023202590

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Nevada Solar One (outlined) and other plants in Clark County, shaded. 35.800, -114.982.

Plant facts

Operator
Acciona Solar Power
Sector
IPP Non-CHP
Grid operator
NEVP
County
Clark County, NV
EIA plant ID
56405
Where Nevada's power comes from → Nevada power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
ONE Solar Thermal without Energy Storage 76 MW 2007 –

Questions

Nevada Solar One, answered

How much power does Nevada Solar One produce?

Nevada Solar One has 76 MW of capacity from one generator. In 2025 it generated 90 GWh, 14% of the most it could have made running flat out all year (its capacity factor).

How many homes does Nevada Solar One power?

Its 2025 output of 90 GWh equals the yearly electricity use of about 8,600 average Nevada homes (868 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Nevada Solar One?

Nevada Solar One is in Clark County, Nevada, at about 35.800°, -114.982°. It is one of 64 power plants of 1 MW or more in the county. The average electricity customer in Clark County goes 1.2 hours a year without power, the 12th most of 12 counties in Nevada. The county's page has the full outage record.

Who operates Nevada Solar One?

It is operated by Acciona Solar Power (EIA sector: IPP Non-CHP), and it feeds NV Energy.

When did Nevada Solar One open?

Its oldest generator still running came online in 2007.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Nevada home's 868 kWh a month in 2025. Methodology.