Nuclear power plant · Oconee, SC
Oconee
Oconee is a 2.7 GW nuclear power plant in Oconee County, South Carolina, operated by Duke Energy Carolinas, LLC. Its oldest generator still running came online in 1973. In 2025 it generated 22 TWh, about what 1,753,000 average South Carolina homes use in a year.
Oconee in context
Among the 4 nuclear plants in South Carolina in the EIA's inventory, it is the largest, about 39% of the state's 6.9 GW of nuclear capacity.
Oconee County has 4 power plants of 1 MW or more with 4.4 GW in all; Oconee is 61% of that.
Its capacity factor of 96% in 2025 is close to the 89% typical for nuclear plants across the US.
The average electricity customer in Oconee County goes 22 hours a year without power, the 8th most of 46 counties in South Carolina. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Oconee (outlined) and other plants in Oconee County, shaded. 34.794, -82.899.
Plant facts
- Operator
- Duke Energy Carolinas, LLC
- Sector
- Electric Utility
- Grid operator
- DUK
- County
- Oconee County, SC
- EIA plant ID
- 3265
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 3 | Nuclear | 893 MW | 1974 | – |
| 1 | Nuclear | 887 MW | 1973 | – |
| 2 | Nuclear | 887 MW | 1974 | – |
Nearby
Other plants in Oconee County
Questions
Oconee, answered
How much power does Oconee produce?
Oconee has 2.7 GW of capacity from 3 generators. In 2025 it generated 22 TWh, 96% of the most it could have made running flat out all year (its capacity factor).
How many homes does Oconee power?
Its 2025 output of 22 TWh equals the yearly electricity use of about 1,753,000 average South Carolina homes (1,066 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Oconee?
Oconee is in Oconee County, South Carolina, at about 34.794°, -82.899°. It is one of 4 power plants of 1 MW or more in the county. The average electricity customer in Oconee County goes 22 hours a year without power, the 8th most of 46 counties in South Carolina. The county's page has the full outage record.
Who operates Oconee?
It is operated by Duke Energy Carolinas, LLC (EIA sector: Electric Utility), and it feeds Duke Energy Carolinas.
When did Oconee open?
Its oldest generator still running came online in 1973.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average South Carolina home's 1,066 kWh a month in 2025. Methodology.