Solar power plant · Sacramento, CA
Rancho Seco Solar II, LLC
Rancho Seco Solar II, LLC is a 160 MW solar power plant in Sacramento County, California, operated by Rancho Seco Solar II, LLC. Its oldest generator still running came online in 2021. In 2025 it generated 275 GWh, about what 46,000 average California homes use in a year.
Rancho Seco Solar II, LLC in context
Among the 967 solar plants in California in the EIA's inventory, it is the 67th largest, about 0.5% of the state's 32 GW of solar capacity.
Sacramento County has 63 power plants of 1 MW or more with 1.8 GW in all; Rancho Seco Solar II, LLC is 9% of that and the largest of 53 solar plants there.
Its capacity factor of 20% in 2025 is close to the 20% typical for solar plants across the US.
The average electricity customer in Sacramento County goes 3.9 hours a year without power, the 46th most of 56 counties in California. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Rancho Seco Solar II, LLC (outlined) and other plants in Sacramento County, shaded. 38.347, -121.120.
Plant facts
- Operator
- Rancho Seco Solar II, LLC
- Sector
- IPP Non-CHP
- Grid operator
- BANC
- County
- Sacramento County, CA
- EIA plant ID
- 63387
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| RSS2 | Solar Photovoltaic | 160 MW | 2021 | – |
Questions
Rancho Seco Solar II, LLC, answered
How much power does Rancho Seco Solar II, LLC produce?
Rancho Seco Solar II, LLC has 160 MW of capacity from one generator. In 2025 it generated 275 GWh, 20% of the most it could have made running flat out all year (its capacity factor).
How many homes does Rancho Seco Solar II, LLC power?
Its 2025 output of 275 GWh equals the yearly electricity use of about 46,000 average California homes (494 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Rancho Seco Solar II, LLC?
Rancho Seco Solar II, LLC is in Sacramento County, California, at about 38.347°, -121.120°. It is one of 63 power plants of 1 MW or more in the county. The average electricity customer in Sacramento County goes 3.9 hours a year without power, the 46th most of 56 counties in California. The county's page has the full outage record.
Who operates Rancho Seco Solar II, LLC?
It is operated by Rancho Seco Solar II, LLC (EIA sector: IPP Non-CHP), and it feeds balancing authority BANC.
When did Rancho Seco Solar II, LLC open?
Its oldest generator still running came online in 2021.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2021–2025). Homes equivalent uses the average California home's 494 kWh a month in 2025. Methodology.