Wind power plant · Lincoln, NM
Red Cloud Wind LLC
Red Cloud Wind LLC is a 350 MW wind power plant in Lincoln County, New Mexico, operated by Pattern Operators LP. Its oldest generator still running came online in 2021. In 2025 it generated 1.2 TWh, about what 154,000 average New Mexico homes use in a year.
Red Cloud Wind LLC in context
Among the 31 wind plants in New Mexico in the EIA's inventory, it is the 4th largest, about 4.3% of the state's 8.1 GW of wind capacity.
Lincoln County has 5 power plants of 1 MW or more with 3.3 GW in all; Red Cloud Wind LLC is 11% of that and the 2nd largest of 4 wind plants there.
Its capacity factor of 39% in 2025 is higher than the 32% typical for wind plants across the US.
The average electricity customer in Lincoln County goes 24 hours a year without power, the 1st most of 20 counties in New Mexico. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Red Cloud Wind LLC (outlined) and other plants in Lincoln County, shaded. 34.274, -105.423.
Plant facts
- Operator
- Pattern Operators LP
- Sector
- IPP Non-CHP
- Grid operator
- PNM
- County
- Lincoln County, NM
- EIA plant ID
- 63981
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Onshore Wind Turbine | 350 MW | 2021 | – |
Nearby
Other plants in Lincoln County
Questions
Red Cloud Wind LLC, answered
How much power does Red Cloud Wind LLC produce?
Red Cloud Wind LLC has 350 MW of capacity from one generator. In 2025 it generated 1.2 TWh, 39% of the most it could have made running flat out all year (its capacity factor).
How many homes does Red Cloud Wind LLC power?
Its 2025 output of 1.2 TWh equals the yearly electricity use of about 154,000 average New Mexico homes (638 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Red Cloud Wind LLC?
Red Cloud Wind LLC is in Lincoln County, New Mexico, at about 34.274°, -105.423°. It is one of 5 power plants of 1 MW or more in the county. The average electricity customer in Lincoln County goes 24 hours a year without power, the 1st most of 20 counties in New Mexico. The county's page has the full outage record.
Who operates Red Cloud Wind LLC?
It is operated by Pattern Operators LP (EIA sector: IPP Non-CHP), and it feeds balancing authority PNM.
When did Red Cloud Wind LLC open?
Its oldest generator still running came online in 2021.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2021–2025). Homes equivalent uses the average New Mexico home's 638 kWh a month in 2025. Methodology.