Red Shield Envir Old Town Facility is a 29 MW biomass power plant in Penobscot County, Maine, operated by ND Paper, Inc.. Its oldest generator still running came online in 1965.
Red Shield Envir Old Town Facility in context
Among the 19 other-fuel plants in Maine in the EIA's inventory, it is the 9th largest, about 1.9% of the state's 1.5 GW of other-fuel capacity.
Penobscot County has 36 power plants of 1 MW or more with 1.0 GW in all; Red Shield Envir Old Town Facility is 3% of that and the largest of 3 biomass plants there.
The average electricity customer in Penobscot County goes 21 hours a year without power, the 11th most of 16 counties in Maine. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Where it is
Red Shield Envir Old Town Facility (outlined) and other plants in Penobscot County, shaded. 44.918, -68.636.
Plant facts
- Operator
- ND Paper, Inc.
- Sector
- Industrial CHP
- Grid operator
- ISNE
- County
- Penobscot County, ME
- EIA plant ID
- 10700
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| TG6 | Wood/Wood Waste Biomass | 16 MW | 1987 | – |
| TG4 | Wood/Wood Waste Biomass | 13 MW | 1965 | – |
Retired
| Generator | Technology | Capacity | Online | Retired |
|---|---|---|---|---|
| TG1 | Petroleum Liquids | 3.5 MW | 1946 | 2002 |
| TG2 | Petroleum Liquids | 3.0 MW | 1956 | 2013 |
| TG5 | Natural Gas Fired Combustion Turbine | 9.5 MW | 2002 | 2013 |
Questions
Red Shield Envir Old Town Facility, answered
How much power does Red Shield Envir Old Town Facility produce?
Red Shield Envir Old Town Facility has 29 MW of capacity from 2 generators. No full year of generation is reported yet.
Where is Red Shield Envir Old Town Facility?
Red Shield Envir Old Town Facility is in Penobscot County, Maine, at about 44.918°, -68.636°. It is one of 36 power plants of 1 MW or more in the county. The average electricity customer in Penobscot County goes 21 hours a year without power, the 11th most of 16 counties in Maine. The county's page has the full outage record.
Who operates Red Shield Envir Old Town Facility?
It is operated by ND Paper, Inc. (EIA sector: Industrial CHP), and it feeds ISO New England.
When did Red Shield Envir Old Town Facility open?
Its oldest generator still running came online in 1965.