Wind power plant · Kiowa, OK

Rocky Ridge Wind Project

Rocky Ridge Wind Project is a 149 MW wind power plant in Kiowa County, Oklahoma, operated by Rocky Ridge Wind Project LLC. Its oldest generator still running came online in 2012. In 2025 it generated 322 GWh, about what 25,000 average Oklahoma homes use in a year.

Capacity149 MWNameplate, September 2026
Generated322 GWhIn 2025
Capacity factor25%Share of the most it could make, 2025
Generators1Oldest from 2012

Rocky Ridge Wind Project in context

Among the 70 wind plants in Oklahoma in the EIA's inventory, it is the 39th largest, about 1.1% of the state's 13 GW of wind capacity.

Kiowa County has 3 power plants of 1 MW or more with 369 MW in all; Rocky Ridge Wind Project is 40% of that.

Its capacity factor of 25% in 2025 is lower than the 32% typical for wind plants across the US.

The average electricity customer in Kiowa County goes 15 hours a year without power, the 6th most of 75 counties in Oklahoma. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

020040060080020182019202020212022202320242025GWh 322
02004006008002019202120232025322

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Rocky Ridge Wind Project (outlined) and other plants in Kiowa County, shaded. 35.136, -99.003.

Plant facts

Operator
Rocky Ridge Wind Project LLC
Sector
IPP Non-CHP
Grid operator
SWPP
County
Kiowa County, OK
EIA plant ID
58078
Where Oklahoma's power comes from → Oklahoma power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
GE 1. Onshore Wind Turbine 149 MW 2012 –

Questions

Rocky Ridge Wind Project, answered

How much power does Rocky Ridge Wind Project produce?

Rocky Ridge Wind Project has 149 MW of capacity from one generator. In 2025 it generated 322 GWh, 25% of the most it could have made running flat out all year (its capacity factor).

How many homes does Rocky Ridge Wind Project power?

Its 2025 output of 322 GWh equals the yearly electricity use of about 25,000 average Oklahoma homes (1,064 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Rocky Ridge Wind Project?

Rocky Ridge Wind Project is in Kiowa County, Oklahoma, at about 35.136°, -99.003°. It is one of 3 power plants of 1 MW or more in the county. The average electricity customer in Kiowa County goes 15 hours a year without power, the 6th most of 75 counties in Oklahoma. The county's page has the full outage record.

Who operates Rocky Ridge Wind Project?

It is operated by Rocky Ridge Wind Project LLC (EIA sector: IPP Non-CHP), and it feeds the Southwest Power Pool.

When did Rocky Ridge Wind Project open?

Its oldest generator still running came online in 2012.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Oklahoma home's 1,064 kWh a month in 2025. Methodology.