Wind power plant · Caledonia, VT
Sheffield Wind
Sheffield Wind is a 40 MW wind power plant in Caledonia County, Vermont, operated by Evergreen Wind, LLC. Its oldest generator still running came online in 2011. In 2025 it generated 68 GWh, about what 9,600 average Vermont homes use in a year.
Sheffield Wind in context
Among the 5 wind plants in Vermont in the EIA's inventory, it is the 2nd largest, about 26% of the state's 151 MW of wind capacity.
Caledonia County has 9 power plants of 1 MW or more with 83 MW in all; Sheffield Wind is 48% of that.
Its capacity factor of 19% in 2025 is lower than the 32% typical for wind plants across the US.
The average electricity customer in Caledonia County goes 7.3 hours a year without power, the 10th most of 14 counties in Vermont. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Sheffield Wind (outlined) and other plants in Caledonia County, shaded. 44.676, -72.101.
Plant facts
- Operator
- Evergreen Wind, LLC
- Sector
- IPP Non-CHP
- Grid operator
- ISNE
- County
- Caledonia County, VT
- EIA plant ID
- 57080
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Onshore Wind Turbine | 40 MW | 2011 | – |
Nearby
Other plants in Caledonia County
Questions
Sheffield Wind, answered
How much power does Sheffield Wind produce?
Sheffield Wind has 40 MW of capacity from one generator. In 2025 it generated 68 GWh, 19% of the most it could have made running flat out all year (its capacity factor).
How many homes does Sheffield Wind power?
Its 2025 output of 68 GWh equals the yearly electricity use of about 9,600 average Vermont homes (591 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Sheffield Wind?
Sheffield Wind is in Caledonia County, Vermont, at about 44.676°, -72.101°. It is one of 9 power plants of 1 MW or more in the county. The average electricity customer in Caledonia County goes 7.3 hours a year without power, the 10th most of 14 counties in Vermont. The county's page has the full outage record.
Who operates Sheffield Wind?
It is operated by Evergreen Wind, LLC (EIA sector: IPP Non-CHP), and it feeds ISO New England.
When did Sheffield Wind open?
Its oldest generator still running came online in 2011.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Vermont home's 591 kWh a month in 2025. Methodology.