Storage power plant · Garfield, OK

Skeleton Creek Energy Center Hybrid

Skeleton Creek Energy Center Hybrid is a 752 MW storage power plant in Garfield County, Oklahoma, operated by Skeleton Creek Energy Center. Its oldest generator still running came online in 2020. In 2025 it generated 899 GWh, about what 70,000 average Oklahoma homes use in a year.

Capacity752 MWNameplate, September 2026
Net energy899 GWhIn 2025
Capacity factor–Not a full year of data
Generators3Oldest from 2020

Skeleton Creek Energy Center Hybrid in context

Among the 6 storage plants in Oklahoma in the EIA's inventory, it is the largest, about 63% of the state's 1.2 GW of storage capacity.

Garfield County has 7 power plants of 1 MW or more with 1.7 GW in all; Skeleton Creek Energy Center Hybrid is 44% of that and the largest of 2 storage plants there.

The average electricity customer in Garfield County goes 4.5 hours a year without power, the 59th most of 75 counties in Oklahoma. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923. Storage uses more energy charging than it returns, so its net figure is negative.

02004006008001,0001,200202020212022202320242025GWh 899
02004006008001,0001,200202020212022202320242025899

Where it is

Skeleton Creek Energy Center Hybrid (outlined) and other plants in Garfield County, shaded. 36.521, -98.034.

Plant facts

Operator
Skeleton Creek Energy Center
Sector
IPP Non-CHP
Grid operator
SWPP
County
Garfield County, OK
EIA plant ID
62494
  • Storage252 MW34%
  • Wind250 MW33%
  • Solar250 MW33%
Where Oklahoma's power comes from → Oklahoma power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
SCBAT Batteries 252 MW · 1,008 MWh 2025 –
SKC Onshore Wind Turbine 250 MW 2020 –
SCSOL Solar Photovoltaic 250 MW 2025 –

Questions

Skeleton Creek Energy Center Hybrid, answered

How much can Skeleton Creek Energy Center Hybrid store and deliver?

Skeleton Creek Energy Center Hybrid can deliver up to 752 MW and hold 1,008 MWh of energy, from 3 storage units. Its net energy in 2025 was 899 GWh: a storage plant uses more energy charging than it returns, so the figure is usually negative.

Where is Skeleton Creek Energy Center Hybrid?

Skeleton Creek Energy Center Hybrid is in Garfield County, Oklahoma, at about 36.521°, -98.034°. It is one of 7 power plants of 1 MW or more in the county. The average electricity customer in Garfield County goes 4.5 hours a year without power, the 59th most of 75 counties in Oklahoma. The county's page has the full outage record.

Who operates Skeleton Creek Energy Center Hybrid?

It is operated by Skeleton Creek Energy Center (EIA sector: IPP Non-CHP), and it feeds the Southwest Power Pool.

When did Skeleton Creek Energy Center Hybrid open?

Its oldest generator still running came online in 2020.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2020–2025). Homes equivalent uses the average Oklahoma home's 1,064 kWh a month in 2025. Methodology.