Soft Maple is a 16 MW hydro power plant in Lewis County, New York, operated by Erie Boulevard Hydropower LP. Its oldest generator still running came online in 1925. In 2025 it generated 32 GWh, about what 4,500 average New York homes use in a year.
Soft Maple in context
Among the 163 hydro plants in New York in the EIA's inventory, it is the 26th largest, about 0.3% of the state's 4.7 GW of hydro capacity.
Lewis County has 29 power plants of 1 MW or more with 785 MW in all; Soft Maple is 2% of that and the largest of 19 hydro plants there.
Its capacity factor of 23% in 2025 is lower than the 34% typical for hydro plants across the US.
The average electricity customer in Lewis County goes 9.4 hours a year without power, the 21st most of 62 counties in New York. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Soft Maple (outlined) and other plants in Lewis County, shaded. 43.921, -75.243.
Plant facts
- Operator
- Erie Boulevard Hydropower LP
- Sector
- IPP Non-CHP
- Grid operator
- NYIS
- County
- Lewis County, NY
- EIA plant ID
- 2610
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Conventional Hydroelectric | 8.0 MW | 1925 | – |
| 2 | Conventional Hydroelectric | 8.0 MW | 1925 | – |
Nearby
Other plants in Lewis County
Questions
Soft Maple, answered
How much power does Soft Maple produce?
Soft Maple has 16 MW of capacity from 2 generators. In 2025 it generated 32 GWh, 23% of the most it could have made running flat out all year (its capacity factor).
How many homes does Soft Maple power?
Its 2025 output of 32 GWh equals the yearly electricity use of about 4,500 average New York homes (586 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Soft Maple?
Soft Maple is in Lewis County, New York, at about 43.921°, -75.243°. It is one of 29 power plants of 1 MW or more in the county. The average electricity customer in Lewis County goes 9.4 hours a year without power, the 21st most of 62 counties in New York. The county's page has the full outage record.
Who operates Soft Maple?
It is operated by Erie Boulevard Hydropower LP (EIA sector: IPP Non-CHP), and it feeds the New York ISO.
When did Soft Maple open?
Its oldest generator still running came online in 1925.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average New York home's 586 kWh a month in 2025. Methodology.