Wind power plant · Washington, ME
Stetson Wind I
Stetson Wind I is a 57 MW wind power plant in Washington County, Maine, operated by Evergreen Wind, LLC. Its oldest generator still running came online in 2009. In 2025 it generated 146 GWh, about what 23,000 average Maine homes use in a year.
Stetson Wind I in context
Among the 22 wind plants in Maine in the EIA's inventory, it is the 8th largest, about 4.7% of the state's 1.2 GW of wind capacity.
Washington County has 8 power plants of 1 MW or more with 316 MW in all; Stetson Wind I is 18% of that and the 2nd largest of 3 wind plants there.
Its capacity factor of 29% in 2025 is close to the 32% typical for wind plants across the US.
The average electricity customer in Washington County goes 19 hours a year without power, the 12th most of 16 counties in Maine. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Stetson Wind I (outlined) and other plants in Washington County, shaded. 45.482, -67.994.
Plant facts
- Operator
- Evergreen Wind, LLC
- Sector
- IPP Non-CHP
- Grid operator
- ISNE
- County
- Washington County, ME
- EIA plant ID
- 56989
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Onshore Wind Turbine | 57 MW | 2009 | – |
Nearby
Other plants in Washington County
Questions
Stetson Wind I, answered
How much power does Stetson Wind I produce?
Stetson Wind I has 57 MW of capacity from one generator. In 2025 it generated 146 GWh, 29% of the most it could have made running flat out all year (its capacity factor).
How many homes does Stetson Wind I power?
Its 2025 output of 146 GWh equals the yearly electricity use of about 23,000 average Maine homes (533 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Stetson Wind I?
Stetson Wind I is in Washington County, Maine, at about 45.482°, -67.994°. It is one of 8 power plants of 1 MW or more in the county. The average electricity customer in Washington County goes 19 hours a year without power, the 12th most of 16 counties in Maine. The county's page has the full outage record.
Who operates Stetson Wind I?
It is operated by Evergreen Wind, LLC (EIA sector: IPP Non-CHP), and it feeds ISO New England.
When did Stetson Wind I open?
Its oldest generator still running came online in 2009.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Maine home's 533 kWh a month in 2025. Methodology.