Wind power plant · Washington, ME
Stetson Wind II
Stetson Wind II is a 26 MW wind power plant in Washington County, Maine, operated by Evergreen Wind, LLC. Its oldest generator still running came online in 2010. In 2025 it generated 55 GWh, about what 8,600 average Maine homes use in a year.
Stetson Wind II in context
Among the 22 wind plants in Maine in the EIA's inventory, it is the 15th largest, about 2.1% of the state's 1.2 GW of wind capacity.
Washington County has 8 power plants of 1 MW or more with 316 MW in all; Stetson Wind II is 8% of that and the 3rd largest of 3 wind plants there.
Its capacity factor of 25% in 2025 is lower than the 32% typical for wind plants across the US.
The average electricity customer in Washington County goes 19 hours a year without power, the 12th most of 16 counties in Maine. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Stetson Wind II (outlined) and other plants in Washington County, shaded. 45.615, -67.971.
Plant facts
- Operator
- Evergreen Wind, LLC
- Sector
- IPP Non-CHP
- Grid operator
- ISNE
- County
- Washington County, ME
- EIA plant ID
- 56991
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Onshore Wind Turbine | 26 MW | 2010 | – |
Nearby
Other plants in Washington County
Questions
Stetson Wind II, answered
How much power does Stetson Wind II produce?
Stetson Wind II has 26 MW of capacity from one generator. In 2025 it generated 55 GWh, 25% of the most it could have made running flat out all year (its capacity factor).
How many homes does Stetson Wind II power?
Its 2025 output of 55 GWh equals the yearly electricity use of about 8,600 average Maine homes (533 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Stetson Wind II?
Stetson Wind II is in Washington County, Maine, at about 45.615°, -67.971°. It is one of 8 power plants of 1 MW or more in the county. The average electricity customer in Washington County goes 19 hours a year without power, the 12th most of 16 counties in Maine. The county's page has the full outage record.
Who operates Stetson Wind II?
It is operated by Evergreen Wind, LLC (EIA sector: IPP Non-CHP), and it feeds ISO New England.
When did Stetson Wind II open?
Its oldest generator still running came online in 2010.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Maine home's 533 kWh a month in 2025. Methodology.