Coal power plant · Carbon, UT

Sunnyside Cogen Associates

Sunnyside Cogen Associates is a 58 MW coal power plant in Carbon County, Utah, operated by Sunnyside Cogeneration Assoc. Its oldest generator still running came online in 1993. In 2025 it generated 226 GWh, about what 25,000 average Utah homes use in a year.

Capacity58 MWNameplate, September 2026
Generated226 GWhIn 2025
Capacity factor44%Share of the most it could make, 2025
Generators1Oldest from 1993

Sunnyside Cogen Associates in context

Among the 4 coal plants in Utah in the EIA's inventory, it is the 4th largest, about 1.9% of the state's 3.1 GW of coal capacity.

Carbon County has 2 power plants of 1 MW or more with 138 MW in all; Sunnyside Cogen Associates is 42% of that.

Its capacity factor of 44% in 2025 is close to the 45% typical for coal plants across the US.

The average electricity customer in Carbon County goes 2.3 hours a year without power, the 16th most of 23 counties in Utah. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

010020030040050020182019202020212022202320242025GWh 226
01002003004005002019202120232025226

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Sunnyside Cogen Associates (outlined) and other plants in Carbon County, shaded. 39.547, -110.392.

Plant facts

Operator
Sunnyside Cogeneration Assoc
Sector
IPP Non-CHP
Grid operator
PACE
County
Carbon County, UT
EIA plant ID
50951
Where Utah's power comes from → Utah power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
GEN1 Conventional Steam Coal 58 MW 1993 –

Nearby

Other plants in Carbon County

Questions

Sunnyside Cogen Associates, answered

How much power does Sunnyside Cogen Associates produce?

Sunnyside Cogen Associates has 58 MW of capacity from one generator. In 2025 it generated 226 GWh, 44% of the most it could have made running flat out all year (its capacity factor).

How many homes does Sunnyside Cogen Associates power?

Its 2025 output of 226 GWh equals the yearly electricity use of about 25,000 average Utah homes (761 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Sunnyside Cogen Associates?

Sunnyside Cogen Associates is in Carbon County, Utah, at about 39.547°, -110.392°. It is one of 2 power plants of 1 MW or more in the county. The average electricity customer in Carbon County goes 2.3 hours a year without power, the 16th most of 23 counties in Utah. The county's page has the full outage record.

Who operates Sunnyside Cogen Associates?

It is operated by Sunnyside Cogeneration Assoc (EIA sector: IPP Non-CHP), and it feeds PacifiCorp East.

When did Sunnyside Cogen Associates open?

Its oldest generator still running came online in 1993.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Utah home's 761 kWh a month in 2025. Methodology.