Wind power plant · Nolan, TX

Sweetwater Wind 5

Sweetwater Wind 5 is a 81 MW wind power plant in Nolan County, Texas, operated by Leeward Asset Management, LLC. Its oldest generator still running came online in 2007. In 2025 it generated 173 GWh, about what 13,000 average Texas homes use in a year.

Capacity81 MWNameplate, September 2026
Generated173 GWhIn 2025
Capacity factor25%Share of the most it could make, 2025
Generators1Oldest from 2007

Sweetwater Wind 5 in context

Among the 230 wind plants in Texas in the EIA's inventory, it is the 198th largest, about 0.2% of the state's 45 GW of wind capacity.

Nolan County has 17 power plants of 1 MW or more with 2.8 GW in all; Sweetwater Wind 5 is 3% of that and the 14th largest of 15 wind plants there.

Its capacity factor of 25% in 2025 is lower than the 32% typical for wind plants across the US.

The average electricity customer in Nolan County goes 7.9 hours a year without power, the 149th most of 240 counties in Texas. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

05010015020025020182019202020212022202320242025GWh 173
0501001502002502019202120232025173

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Sweetwater Wind 5 (outlined) and other plants in Nolan County, shaded. 32.237, -100.483.

Plant facts

Operator
Leeward Asset Management, LLC
Sector
IPP Non-CHP
Grid operator
ERCO
County
Nolan County, TX
EIA plant ID
56372
Where Texas's power comes from → Texas power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
SW5 Onshore Wind Turbine 81 MW 2007 –

Questions

Sweetwater Wind 5, answered

How much power does Sweetwater Wind 5 produce?

Sweetwater Wind 5 has 81 MW of capacity from one generator. In 2025 it generated 173 GWh, 25% of the most it could have made running flat out all year (its capacity factor).

How many homes does Sweetwater Wind 5 power?

Its 2025 output of 173 GWh equals the yearly electricity use of about 13,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Sweetwater Wind 5?

Sweetwater Wind 5 is in Nolan County, Texas, at about 32.237°, -100.483°. It is one of 17 power plants of 1 MW or more in the county. The average electricity customer in Nolan County goes 7.9 hours a year without power, the 149th most of 240 counties in Texas. The county's page has the full outage record.

Who operates Sweetwater Wind 5?

It is operated by Leeward Asset Management, LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.

When did Sweetwater Wind 5 open?

Its oldest generator still running came online in 2007.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.