Solar power plant · Clark, NV
Techren Solar I LLC
Techren Solar I LLC is a 100 MW solar power plant in Clark County, Nevada, operated by Techren Solar I LLC. Its oldest generator still running came online in 2019. In 2025 it generated 224 GWh, about what 22,000 average Nevada homes use in a year.
Techren Solar I LLC in context
Among the 58 solar plants in Nevada in the EIA's inventory, it is the 22nd largest, about 1.6% of the state's 6.2 GW of solar capacity.
Clark County has 64 power plants of 1 MW or more with 14 GW in all; Techren Solar I LLC is 1% of that and the 16th largest of 45 solar plants there.
Its capacity factor of 26% in 2025 is higher than the 20% typical for solar plants across the US.
The average electricity customer in Clark County goes 1.2 hours a year without power, the 12th most of 12 counties in Nevada. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Techren Solar I LLC (outlined) and other plants in Clark County, shaded. 35.851, -114.974.
Plant facts
- Operator
- Techren Solar I LLC
- Sector
- IPP Non-CHP
- Grid operator
- NEVP
- County
- Clark County, NV
- EIA plant ID
- 61611
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| TECH1 | Solar Photovoltaic | 100 MW | 2019 | – |
Questions
Techren Solar I LLC, answered
How much power does Techren Solar I LLC produce?
Techren Solar I LLC has 100 MW of capacity from one generator. In 2025 it generated 224 GWh, 26% of the most it could have made running flat out all year (its capacity factor).
How many homes does Techren Solar I LLC power?
Its 2025 output of 224 GWh equals the yearly electricity use of about 22,000 average Nevada homes (868 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Techren Solar I LLC?
Techren Solar I LLC is in Clark County, Nevada, at about 35.851°, -114.974°. It is one of 64 power plants of 1 MW or more in the county. The average electricity customer in Clark County goes 1.2 hours a year without power, the 12th most of 12 counties in Nevada. The county's page has the full outage record.
Who operates Techren Solar I LLC?
It is operated by Techren Solar I LLC (EIA sector: IPP Non-CHP), and it feeds NV Energy.
When did Techren Solar I LLC open?
Its oldest generator still running came online in 2019.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2019–2025). Homes equivalent uses the average Nevada home's 868 kWh a month in 2025. Methodology.