Solar power plant · Clark, NV

Techren Solar II LLC

Techren Solar II LLC is a 200 MW solar power plant in Clark County, Nevada, operated by Techren Solar II LLC. Its oldest generator still running came online in 2019. In 2025 it generated 492 GWh, about what 47,000 average Nevada homes use in a year.

Capacity200 MWNameplate, September 2026
Generated492 GWhIn 2025
Capacity factor28%Share of the most it could make, 2025
Generators1Oldest from 2019

Techren Solar II LLC in context

Among the 58 solar plants in Nevada in the EIA's inventory, it is the 13th largest, about 3.2% of the state's 6.2 GW of solar capacity.

Clark County has 64 power plants of 1 MW or more with 14 GW in all; Techren Solar II LLC is 1% of that and the 11th largest of 45 solar plants there.

Its capacity factor of 28% in 2025 is higher than the 20% typical for solar plants across the US.

The average electricity customer in Clark County goes 1.2 hours a year without power, the 12th most of 12 counties in Nevada. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

02004006008002019202020212022202320242025GWh 492
02004006008002019202120232025492

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Techren Solar II LLC (outlined) and other plants in Clark County, shaded. 35.867, -114.956.

Plant facts

Operator
Techren Solar II LLC
Sector
IPP Non-CHP
Grid operator
NEVP
County
Clark County, NV
EIA plant ID
61930
Where Nevada's power comes from → Nevada power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
TECH2 Solar Photovoltaic 200 MW 2019 –

Questions

Techren Solar II LLC, answered

How much power does Techren Solar II LLC produce?

Techren Solar II LLC has 200 MW of capacity from one generator. In 2025 it generated 492 GWh, 28% of the most it could have made running flat out all year (its capacity factor).

How many homes does Techren Solar II LLC power?

Its 2025 output of 492 GWh equals the yearly electricity use of about 47,000 average Nevada homes (868 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Techren Solar II LLC?

Techren Solar II LLC is in Clark County, Nevada, at about 35.867°, -114.956°. It is one of 64 power plants of 1 MW or more in the county. The average electricity customer in Clark County goes 1.2 hours a year without power, the 12th most of 12 counties in Nevada. The county's page has the full outage record.

Who operates Techren Solar II LLC?

It is operated by Techren Solar II LLC (EIA sector: IPP Non-CHP), and it feeds NV Energy.

When did Techren Solar II LLC open?

Its oldest generator still running came online in 2019.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2019–2025). Homes equivalent uses the average Nevada home's 868 kWh a month in 2025. Methodology.