Natural gas power plant · Heard, GA
Tenaska Georgia Generation Facility
Tenaska Georgia Generation Facility is a 1.1 GW natural gas power plant in Heard County, Georgia, operated by Tenaska Georgia Partners LP. Its oldest generator still running came online in 2001. In 2025 it generated 103 GWh, about what 7,900 average Georgia homes use in a year.
Tenaska Georgia Generation Facility in context
Among the 30 natural gas plants in Georgia in the EIA's inventory, it is the 5th largest, about 5.9% of the state's 19 GW of natural gas capacity.
Heard County has 5 power plants of 1 MW or more with 4.0 GW in all; Tenaska Georgia Generation Facility is 28% of that and the 2nd largest of 5 natural gas plants there.
Its capacity factor of 1% in 2025 is lower than the 23% typical for natural gas plants across the US.
The average electricity customer in Heard County goes 7.8 hours a year without power, the 88th most of 156 counties in Georgia. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Tenaska Georgia Generation Facility (outlined) and other plants in Heard County, shaded. 33.352, -85.000.
Plant facts
- Operator
- Tenaska Georgia Partners LP
- Sector
- IPP Non-CHP
- Grid operator
- SOCO
- County
- Heard County, GA
- EIA plant ID
- 55061
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| GTG1 | Natural Gas Fired Combustion Turbine | 183 MW | 2001 | – |
| GTG2 | Natural Gas Fired Combustion Turbine | 183 MW | 2001 | – |
| GTG3 | Natural Gas Fired Combustion Turbine | 183 MW | 2001 | – |
| GTG4 | Natural Gas Fired Combustion Turbine | 183 MW | 2002 | – |
| GTG5 | Natural Gas Fired Combustion Turbine | 183 MW | 2002 | – |
| GTG6 | Natural Gas Fired Combustion Turbine | 183 MW | 2002 | – |
Nearby
Other plants in Heard County
Questions
Tenaska Georgia Generation Facility, answered
How much power does Tenaska Georgia Generation Facility produce?
Tenaska Georgia Generation Facility has 1.1 GW of capacity from 6 generators. In 2025 it generated 103 GWh, 1% of the most it could have made running flat out all year (its capacity factor).
How many homes does Tenaska Georgia Generation Facility power?
Its 2025 output of 103 GWh equals the yearly electricity use of about 7,900 average Georgia homes (1,077 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Tenaska Georgia Generation Facility?
Tenaska Georgia Generation Facility is in Heard County, Georgia, at about 33.352°, -85.000°. It is one of 5 power plants of 1 MW or more in the county. The average electricity customer in Heard County goes 7.8 hours a year without power, the 88th most of 156 counties in Georgia. The county's page has the full outage record.
Who operates Tenaska Georgia Generation Facility?
It is operated by Tenaska Georgia Partners LP (EIA sector: IPP Non-CHP), and it feeds Southern Company.
When did Tenaska Georgia Generation Facility open?
Its oldest generator still running came online in 2001.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Georgia home's 1,077 kWh a month in 2025. Methodology.