Natural gas power plant · Heard, GA

Wansley Combined Cycle

Wansley Combined Cycle is a 1.2 GW natural gas power plant in Heard County, Georgia, operated by Southern Power Co. Its oldest generator still running came online in 2002. In 2025 it generated 7.6 TWh, about what 591,000 average Georgia homes use in a year.

Capacity1.2 GWNameplate, September 2026
Generated7.6 TWhIn 2025
Capacity factor70%Share of the most it could make, 2025
Generators6Oldest from 2002

Wansley Combined Cycle in context

Among the 30 natural gas plants in Georgia in the EIA's inventory, it is the 3rd largest, about 6.7% of the state's 19 GW of natural gas capacity.

Heard County has 5 power plants of 1 MW or more with 4.0 GW in all; Wansley Combined Cycle is 31% of that and the largest of 5 natural gas plants there.

Its capacity factor of 70% in 2025 is higher than the 23% typical for natural gas plants across the US.

The average electricity customer in Heard County goes 7.8 hours a year without power, the 88th most of 156 counties in Georgia. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

02,0004,0006,0008,00010,00020182019202020212022202320242025GWh 7,633
02,0004,0006,0008,00010,00020192021202320257,633

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Wansley Combined Cycle (outlined) and other plants in Heard County, shaded. 33.406, -85.037.

Plant facts

Operator
Southern Power Co
Sector
IPP Non-CHP
Grid operator
SOCO
County
Heard County, GA
EIA plant ID
55965
Where Georgia's power comes from → Georgia power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
ST6 Natural Gas Fired Combined Cycle 213 MW 2002 –
ST7 Natural Gas Fired Combined Cycle 213 MW 2002 –
CT6A Natural Gas Fired Combined Cycle 203 MW 2002 –
CT6B Natural Gas Fired Combined Cycle 203 MW 2002 –
CT7A Natural Gas Fired Combined Cycle 203 MW 2002 –
CT7B Natural Gas Fired Combined Cycle 203 MW 2002 –

Questions

Wansley Combined Cycle, answered

How much power does Wansley Combined Cycle produce?

Wansley Combined Cycle has 1.2 GW of capacity from 6 generators. In 2025 it generated 7.6 TWh, 70% of the most it could have made running flat out all year (its capacity factor).

How many homes does Wansley Combined Cycle power?

Its 2025 output of 7.6 TWh equals the yearly electricity use of about 591,000 average Georgia homes (1,077 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Wansley Combined Cycle?

Wansley Combined Cycle is in Heard County, Georgia, at about 33.406°, -85.037°. It is one of 5 power plants of 1 MW or more in the county. The average electricity customer in Heard County goes 7.8 hours a year without power, the 88th most of 156 counties in Georgia. The county's page has the full outage record.

Who operates Wansley Combined Cycle?

It is operated by Southern Power Co (EIA sector: IPP Non-CHP), and it feeds Southern Company.

When did Wansley Combined Cycle open?

Its oldest generator still running came online in 2002.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Georgia home's 1,077 kWh a month in 2025. Methodology.