Natural gas power plant · San Diego, CA

University of California San Diego Hybri

University of California San Diego Hybri is a 33 MW natural gas power plant in San Diego County, California, operated by University of California San Diego. Its oldest generator still running came online in 2001. In 2025 it generated 207 GWh, about what 35,000 average California homes use in a year.

Capacity33 MWNameplate, September 2026
Generated207 GWhIn 2025
Capacity factor72%Share of the most it could make, 2025
Generators3Oldest from 2001

University of California San Diego Hybri in context

Among the 304 natural gas plants in California in the EIA's inventory, it is the 161st largest, about 0.1% of the state's 41 GW of natural gas capacity.

San Diego County has 107 power plants of 1 MW or more with 5.1 GW in all; University of California San Diego Hybri is 1% of that and the 15th largest of 29 natural gas plants there.

Its capacity factor of 72% in 2025 is higher than the 23% typical for natural gas plants across the US.

The average electricity customer in San Diego County goes 3.3 hours a year without power, the 49th most of 56 counties in California. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

010020030020182019202020212022202320242025GWh 207
01002003002019202120232025207

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

University of California San Diego Hybri (outlined) and other plants in San Diego County, shaded. 32.875, -117.239.

Plant facts

Operator
University of California San Diego
Sector
Commercial CHP
Grid operator
CISO
County
San Diego County, CA
EIA plant ID
57584
Where California's power comes from → California power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
NT2 Natural Gas Fired Combined Cycle 15 MW 2001 –
ST1 Natural Gas Fired Combined Cycle 15 MW 2001 –
STG Natural Gas Fired Combined Cycle 3.0 MW 2001 –

Retired

GeneratorTechnologyCapacityOnlineRetired
BS1Batteries2.5 MW20152025

Questions

University of California San Diego Hybri, answered

How much power does University of California San Diego Hybri produce?

University of California San Diego Hybri has 33 MW of capacity from 3 generators. In 2025 it generated 207 GWh, 72% of the most it could have made running flat out all year (its capacity factor).

How many homes does University of California San Diego Hybri power?

Its 2025 output of 207 GWh equals the yearly electricity use of about 35,000 average California homes (494 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is University of California San Diego Hybri?

University of California San Diego Hybri is in San Diego County, California, at about 32.875°, -117.239°. It is one of 107 power plants of 1 MW or more in the county. The average electricity customer in San Diego County goes 3.3 hours a year without power, the 49th most of 56 counties in California. The county's page has the full outage record.

Who operates University of California San Diego Hybri?

It is operated by University of California San Diego (EIA sector: Commercial CHP), and it feeds the California ISO.

When did University of California San Diego Hybri open?

Its oldest generator still running came online in 2001.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average California home's 494 kWh a month in 2025. Methodology.