Solar power plant · Limestone, TX

Waco Solar

Waco Solar is a 400 MW solar power plant in Limestone County, Texas, operated by Waco Solar, LLC. Its oldest generator still running came online in 2024. In 2025 it generated 911 GWh, about what 68,000 average Texas homes use in a year.

Capacity400 MWNameplate, September 2026
Generated911 GWhIn 2025
Capacity factor26%Share of the most it could make, 2025
Generators1Oldest from 2024

Waco Solar in context

Among the 250 solar plants in Texas in the EIA's inventory, it is the 21st largest, about 1.1% of the state's 37 GW of solar capacity.

Limestone County has 7 power plants of 1 MW or more with 3.1 GW in all; Waco Solar is 13% of that and the largest of 4 solar plants there.

Its capacity factor of 26% in 2025 is higher than the 20% typical for solar plants across the US.

The average electricity customer in Limestone County goes 15 hours a year without power, the 71st most of 240 counties in Texas. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

02004006008001,0001,20020242025GWh 911
02004006008001,0001,20020242025911

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Waco Solar (outlined) and other plants in Limestone County, shaded. 31.710, -96.819.

Plant facts

Operator
Waco Solar, LLC
Sector
IPP Non-CHP
Grid operator
ERCO
County
Limestone County, TX
EIA plant ID
65762
Where Texas's power comes from → Texas power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
SWACO Solar Photovoltaic 400 MW 2024 –

Nearby

Other plants in Limestone County

Questions

Waco Solar, answered

How much power does Waco Solar produce?

Waco Solar has 400 MW of capacity from one generator. In 2025 it generated 911 GWh, 26% of the most it could have made running flat out all year (its capacity factor).

How many homes does Waco Solar power?

Its 2025 output of 911 GWh equals the yearly electricity use of about 68,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Waco Solar?

Waco Solar is in Limestone County, Texas, at about 31.710°, -96.819°. It is one of 7 power plants of 1 MW or more in the county. The average electricity customer in Limestone County goes 15 hours a year without power, the 71st most of 240 counties in Texas. The county's page has the full outage record.

Who operates Waco Solar?

It is operated by Waco Solar, LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.

When did Waco Solar open?

Its oldest generator still running came online in 2024.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2024–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.