Hydro power plant · Somerset, ME

Williams Hydro

Williams Hydro is a 13 MW hydro power plant in Somerset County, Maine, operated by Brookfield White Pine Hydro LLC. Its oldest generator still running came online in 1939. In 2025 it generated 64 GWh, about what 9,900 average Maine homes use in a year.

Capacity13 MWNameplate, September 2026
Generated64 GWhIn 2025
Capacity factor56%Share of the most it could make, 2025
Generators2Oldest from 1939

Williams Hydro in context

Among the 48 hydro plants in Maine in the EIA's inventory, it is the 13th largest, about 1.9% of the state's 700 MW of hydro capacity.

Somerset County has 37 power plants of 1 MW or more with 498 MW in all; Williams Hydro is 3% of that and the 4th largest of 8 hydro plants there.

Its capacity factor of 56% in 2025 is higher than the 34% typical for hydro plants across the US.

The average electricity customer in Somerset County goes 42 hours a year without power, the 2nd most of 16 counties in Maine. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

02040608010012020182019202020212022202320242025GWh 64
020406080100120201920212023202564

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Williams Hydro (outlined) and other plants in Somerset County, shaded. 44.959, -69.870.

Plant facts

Operator
Brookfield White Pine Hydro LLC
Sector
IPP Non-CHP
Grid operator
ISNE
County
Somerset County, ME
EIA plant ID
1510
Where Maine's power comes from → Maine power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
WI1 Conventional Hydroelectric 7.0 MW 1939 –
WI2 Conventional Hydroelectric 6.0 MW 1950 –

Nearby

Other plants in Somerset County

Questions

Williams Hydro, answered

How much power does Williams Hydro produce?

Williams Hydro has 13 MW of capacity from 2 generators. In 2025 it generated 64 GWh, 56% of the most it could have made running flat out all year (its capacity factor).

How many homes does Williams Hydro power?

Its 2025 output of 64 GWh equals the yearly electricity use of about 9,900 average Maine homes (533 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Williams Hydro?

Williams Hydro is in Somerset County, Maine, at about 44.959°, -69.870°. It is one of 37 power plants of 1 MW or more in the county. The average electricity customer in Somerset County goes 42 hours a year without power, the 2nd most of 16 counties in Maine. The county's page has the full outage record.

Who operates Williams Hydro?

It is operated by Brookfield White Pine Hydro LLC (EIA sector: IPP Non-CHP), and it feeds ISO New England.

When did Williams Hydro open?

Its oldest generator still running came online in 1939.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Maine home's 533 kWh a month in 2025. Methodology.