Coal power plant · Campbell, WY

Wygen 2

Wygen 2 is a 95 MW coal power plant in Campbell County, Wyoming, operated by Black Hills Power, Inc.. Its oldest generator still running came online in 2008. In 2025 it generated 596 GWh, about what 59,000 average Wyoming homes use in a year.

Capacity95 MWNameplate, September 2026
Generated596 GWhIn 2025
Capacity factor72%Share of the most it could make, 2025
Generators1Oldest from 2008

Wygen 2 in context

Among the 11 coal plants in Wyoming in the EIA's inventory, it is the 8th largest, about 2.0% of the state's 4.7 GW of coal capacity.

Campbell County has 9 power plants of 1 MW or more with 1.4 GW in all; Wygen 2 is 7% of that and the 5th largest of 6 coal plants there.

Its capacity factor of 72% in 2025 is higher than the 45% typical for coal plants across the US.

The average electricity customer in Campbell County goes 3.3 hours a year without power, the 6th most of 20 counties in Wyoming. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

02004006008001,00020182019202020212022202320242025GWh 596
02004006008001,0002019202120232025596

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Wygen 2 (outlined) and other plants in Campbell County, shaded. 44.292, -105.381.

Plant facts

Operator
Black Hills Power, Inc.
Sector
Electric Utility
Grid operator
WACM
County
Campbell County, WY
EIA plant ID
56319
Where Wyoming's power comes from → Wyoming power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
0001 Conventional Steam Coal 95 MW 2008 –

Questions

Wygen 2, answered

How much power does Wygen 2 produce?

Wygen 2 has 95 MW of capacity from one generator. In 2025 it generated 596 GWh, 72% of the most it could have made running flat out all year (its capacity factor).

How many homes does Wygen 2 power?

Its 2025 output of 596 GWh equals the yearly electricity use of about 59,000 average Wyoming homes (835 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Wygen 2?

Wygen 2 is in Campbell County, Wyoming, at about 44.292°, -105.381°. It is one of 9 power plants of 1 MW or more in the county. The average electricity customer in Campbell County goes 3.3 hours a year without power, the 6th most of 20 counties in Wyoming. The county's page has the full outage record.

Who operates Wygen 2?

It is operated by Black Hills Power, Inc. (EIA sector: Electric Utility), and it feeds WAPA Rocky Mountain.

When did Wygen 2 open?

Its oldest generator still running came online in 2008.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Wyoming home's 835 kWh a month in 2025. Methodology.