Wind power plant · Klickitat, WA
Big Horn Wind II
Big Horn Wind II is a 50 MW wind power plant in Klickitat County, Washington, operated by Avangrid Power LLC. Its oldest generator still running came online in 2011. In 2025 it generated 105 GWh, about what 9,300 average Washington homes use in a year.
Big Horn Wind II in context
Among the 23 wind plants in Washington in the EIA's inventory, it is the 20th largest, about 1.5% of the state's 3.4 GW of wind capacity.
Klickitat County has 11 power plants of 1 MW or more with 1.7 GW in all; Big Horn Wind II is 3% of that and the 8th largest of 9 wind plants there.
Its capacity factor of 24% in 2025 is lower than the 32% typical for wind plants across the US.
The average electricity customer in Klickitat County goes 0.6 hours a year without power. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Big Horn Wind II (outlined) and other plants in Klickitat County, shaded. 45.919, -120.304.
Plant facts
- Operator
- Avangrid Power LLC
- Sector
- IPP Non-CHP
- Grid operator
- AVRN
- County
- Klickitat County, WA
- EIA plant ID
- 57319
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Onshore Wind Turbine | 50 MW | 2011 | – |
Questions
Big Horn Wind II, answered
How much power does Big Horn Wind II produce?
Big Horn Wind II has 50 MW of capacity from one generator. In 2025 it generated 105 GWh, 24% of the most it could have made running flat out all year (its capacity factor).
How many homes does Big Horn Wind II power?
Its 2025 output of 105 GWh equals the yearly electricity use of about 9,300 average Washington homes (945 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Big Horn Wind II?
Big Horn Wind II is in Klickitat County, Washington, at about 45.919°, -120.304°. It is one of 11 power plants of 1 MW or more in the county. The average electricity customer in Klickitat County goes 0.6 hours a year without power. The county's page has the full outage record.
Who operates Big Horn Wind II?
It is operated by Avangrid Power LLC (EIA sector: IPP Non-CHP), and it feeds balancing authority AVRN.
When did Big Horn Wind II open?
Its oldest generator still running came online in 2011.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Washington home's 945 kWh a month in 2025. Methodology.