Solar power plant · Nash, NC
Brantley Solar
Brantley Solar is a 50 MW solar power plant in Nash County, North Carolina, operated by John Laing US Solar Corp.. Its oldest generator still running came online in 2018. In 2025 it generated 98 GWh, about what 7,900 average North Carolina homes use in a year.
Brantley Solar in context
Among the 756 solar plants in North Carolina in the EIA's inventory, it is the 35th largest, about 0.7% of the state's 7.1 GW of solar capacity.
Nash County has 32 power plants of 1 MW or more with 379 MW in all; Brantley Solar is 13% of that and the 3rd largest of 32 solar plants there.
Its capacity factor of 22% in 2025 is close to the 20% typical for solar plants across the US.
The average electricity customer in Nash County goes 6.1 hours a year without power, the 70th most of 100 counties in North Carolina. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Brantley Solar (outlined) and other plants in Nash County, shaded. 35.890, -78.155.
Plant facts
- Operator
- John Laing US Solar Corp.
- Sector
- IPP Non-CHP
- Grid operator
- CPLE
- County
- Nash County, NC
- EIA plant ID
- 60623
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| PV1 | Solar Photovoltaic | 50 MW | 2018 | – |
Nearby
Other plants in Nash County
Questions
Brantley Solar, answered
How much power does Brantley Solar produce?
Brantley Solar has 50 MW of capacity from one generator. In 2025 it generated 98 GWh, 22% of the most it could have made running flat out all year (its capacity factor).
How many homes does Brantley Solar power?
Its 2025 output of 98 GWh equals the yearly electricity use of about 7,900 average North Carolina homes (1,044 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Brantley Solar?
Brantley Solar is in Nash County, North Carolina, at about 35.890°, -78.155°. It is one of 32 power plants of 1 MW or more in the county. The average electricity customer in Nash County goes 6.1 hours a year without power, the 70th most of 100 counties in North Carolina. The county's page has the full outage record.
Who operates Brantley Solar?
It is operated by John Laing US Solar Corp. (EIA sector: IPP Non-CHP), and it feeds balancing authority CPLE.
When did Brantley Solar open?
Its oldest generator still running came online in 2018.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average North Carolina home's 1,044 kWh a month in 2025. Methodology.