East Nash PV2 is a 23 MW solar power plant in Nash County, North Carolina, operated by Modal Power LLC. Its oldest generator still running came online in 2023. In 2025 it generated 53 GWh, about what 4,200 average North Carolina homes use in a year.
East Nash PV2 in context
Among the 756 solar plants in North Carolina in the EIA's inventory, it is the 53rd largest, about 0.3% of the state's 7.1 GW of solar capacity.
Nash County has 32 power plants of 1 MW or more with 379 MW in all; East Nash PV2 is 6% of that and the 4th largest of 32 solar plants there.
Its capacity factor of 26% in 2025 is higher than the 20% typical for solar plants across the US.
The average electricity customer in Nash County goes 6.1 hours a year without power, the 70th most of 100 counties in North Carolina. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
East Nash PV2 (outlined) and other plants in Nash County, shaded. 35.956, -78.094.
Plant facts
- Operator
- Modal Power LLC
- Sector
- IPP Non-CHP
- Grid operator
- CPLE
- County
- Nash County, NC
- EIA plant ID
- 63789
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| ENSH2 | Solar Photovoltaic | 23 MW | 2023 | – |
Nearby
Other plants in Nash County
Questions
East Nash PV2, answered
How much power does East Nash PV2 produce?
East Nash PV2 has 23 MW of capacity from one generator. In 2025 it generated 53 GWh, 26% of the most it could have made running flat out all year (its capacity factor).
How many homes does East Nash PV2 power?
Its 2025 output of 53 GWh equals the yearly electricity use of about 4,200 average North Carolina homes (1,044 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is East Nash PV2?
East Nash PV2 is in Nash County, North Carolina, at about 35.956°, -78.094°. It is one of 32 power plants of 1 MW or more in the county. The average electricity customer in Nash County goes 6.1 hours a year without power, the 70th most of 100 counties in North Carolina. The county's page has the full outage record.
Who operates East Nash PV2?
It is operated by Modal Power LLC (EIA sector: IPP Non-CHP), and it feeds balancing authority CPLE.
When did East Nash PV2 open?
Its oldest generator still running came online in 2023.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2023–2025). Homes equivalent uses the average North Carolina home's 1,044 kWh a month in 2025. Methodology.