Wind power plant · Borden, TX
Bull Creek Wind
Bull Creek Wind is a 180 MW wind power plant in Borden County, Texas, operated by Bull Creek Wind LLC. Its oldest generator still running came online in 2008. In 2025 it generated 260 GWh, about what 19,000 average Texas homes use in a year.
Bull Creek Wind in context
Among the 230 wind plants in Texas in the EIA's inventory, it is the 122nd largest, about 0.4% of the state's 45 GW of wind capacity.
Borden County has 7 power plants of 1 MW or more with 1.5 GW in all; Bull Creek Wind is 12% of that and the 2nd largest of 4 wind plants there.
Its capacity factor of 17% in 2025 is lower than the 32% typical for wind plants across the US.
The average electricity customer in Borden County goes 33 hours a year without power. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Bull Creek Wind (outlined) and other plants in Borden County, shaded. 32.929, -101.579.
Plant facts
- Operator
- Bull Creek Wind LLC
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Borden County, TX
- EIA plant ID
- 56956
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 001 | Onshore Wind Turbine | 180 MW | 2008 | – |
Questions
Bull Creek Wind, answered
How much power does Bull Creek Wind produce?
Bull Creek Wind has 180 MW of capacity from one generator. In 2025 it generated 260 GWh, 17% of the most it could have made running flat out all year (its capacity factor).
How many homes does Bull Creek Wind power?
Its 2025 output of 260 GWh equals the yearly electricity use of about 19,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Bull Creek Wind?
Bull Creek Wind is in Borden County, Texas, at about 32.929°, -101.579°. It is one of 7 power plants of 1 MW or more in the county. The average electricity customer in Borden County goes 33 hours a year without power. The county's page has the full outage record.
Who operates Bull Creek Wind?
It is operated by Bull Creek Wind LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did Bull Creek Wind open?
Its oldest generator still running came online in 2008.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.