Wind power plant · Borden, TX

Post Wind Farm LP

Post Wind Farm LP is a 84 MW wind power plant in Borden County, Texas, operated by FPL Energy Red Canyon LLC. Its oldest generator still running came online in 2006. In 2025 it generated 312 GWh, about what 23,000 average Texas homes use in a year.

Capacity84 MWNameplate, September 2026
Generated312 GWhIn 2025
Capacity factor42%Share of the most it could make, 2025
Generators1Oldest from 2006

Post Wind Farm LP in context

Among the 230 wind plants in Texas in the EIA's inventory, it is the 195th largest, about 0.2% of the state's 45 GW of wind capacity.

Borden County has 7 power plants of 1 MW or more with 1.5 GW in all; Post Wind Farm LP is 6% of that and the 4th largest of 4 wind plants there.

Its capacity factor of 42% in 2025 is higher than the 32% typical for wind plants across the US.

The average electricity customer in Borden County goes 33 hours a year without power. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

010020030040020182019202020212022202320242025GWh 312
01002003004002019202120232025312

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Post Wind Farm LP (outlined) and other plants in Borden County, shaded. 32.925, -101.219.

Plant facts

Operator
FPL Energy Red Canyon LLC
Sector
IPP Non-CHP
Grid operator
ERCO
County
Borden County, TX
EIA plant ID
56457
Where Texas's power comes from → Texas power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
1 Onshore Wind Turbine 84 MW 2006 –

Questions

Post Wind Farm LP, answered

How much power does Post Wind Farm LP produce?

Post Wind Farm LP has 84 MW of capacity from one generator. In 2025 it generated 312 GWh, 42% of the most it could have made running flat out all year (its capacity factor).

How many homes does Post Wind Farm LP power?

Its 2025 output of 312 GWh equals the yearly electricity use of about 23,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Post Wind Farm LP?

Post Wind Farm LP is in Borden County, Texas, at about 32.925°, -101.219°. It is one of 7 power plants of 1 MW or more in the county. The average electricity customer in Borden County goes 33 hours a year without power. The county's page has the full outage record.

Who operates Post Wind Farm LP?

It is operated by FPL Energy Red Canyon LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.

When did Post Wind Farm LP open?

Its oldest generator still running came online in 2006.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.