Cantua Solar Station is a 20 MW solar power plant in Fresno County, California, operated by Pacific Gas & Electric Co.. Its oldest generator still running came online in 2012. In 2025 it generated 23 GWh, about what 3,900 average California homes use in a year.

Capacity20 MWNameplate, September 2026
Generated23 GWhIn 2025
Capacity factor13%Share of the most it could make, 2025
Generators1Oldest from 2012

Cantua Solar Station in context

Among the 967 solar plants in California in the EIA's inventory, it is the 169th largest, about 0.1% of the state's 32 GW of solar capacity.

Fresno County has 105 power plants of 1 MW or more with 5.9 GW in all; Cantua Solar Station is 0% of that and the 14th largest of 73 solar plants there.

Its capacity factor of 13% in 2025 is lower than the 20% typical for solar plants across the US.

The average electricity customer in Fresno County goes 3.5 hours a year without power, the 48th most of 56 counties in California. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

0102030405020182019202020212022202320242025GWh 23
01020304050201920212023202523

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Cantua Solar Station (outlined) and other plants in Fresno County, shaded. 36.425, -120.344.

Plant facts

Operator
Pacific Gas & Electric Co.
Sector
Electric Utility
Grid operator
CISO
County
Fresno County, CA
EIA plant ID
57522
Where California's power comes from → California power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
1 Solar Photovoltaic 20 MW 2012 –

Questions

Cantua Solar Station, answered

How much power does Cantua Solar Station produce?

Cantua Solar Station has 20 MW of capacity from one generator. In 2025 it generated 23 GWh, 13% of the most it could have made running flat out all year (its capacity factor).

How many homes does Cantua Solar Station power?

Its 2025 output of 23 GWh equals the yearly electricity use of about 3,900 average California homes (494 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Cantua Solar Station?

Cantua Solar Station is in Fresno County, California, at about 36.425°, -120.344°. It is one of 105 power plants of 1 MW or more in the county. The average electricity customer in Fresno County goes 3.5 hours a year without power, the 48th most of 56 counties in California. The county's page has the full outage record.

Who operates Cantua Solar Station?

It is operated by Pacific Gas & Electric Co. (EIA sector: Electric Utility), and it feeds the California ISO.

When did Cantua Solar Station open?

Its oldest generator still running came online in 2012.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average California home's 494 kWh a month in 2025. Methodology.