Storage power plant · Riverside, CA
Carris Storage I
Carris Storage I is a 10 MW storage power plant in Riverside County, California, operated by Hecate Grid Carris Storage 1 LLC. Its oldest generator still running came online in 2025.
Carris Storage I in context
Among the 156 storage plants in California in the EIA's inventory, it is the 105th largest, about 0.1% of the state's 13 GW of storage capacity.
Riverside County has 121 power plants of 1 MW or more with 11 GW in all; Carris Storage I is 0% of that and the 12th largest of 14 storage plants there.
The average electricity customer in Riverside County goes 5.0 hours a year without power, the 37th most of 56 counties in California. The county's page has the full outage record.
Where it is
Carris Storage I (outlined) and other plants in Riverside County, shaded. 33.808, -116.494.
Plant facts
- Operator
- Hecate Grid Carris Storage 1 LLC
- Sector
- IPP Non-CHP
- Grid operator
- CISO
- County
- Riverside County, CA
- EIA plant ID
- 65733
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| HECAR | Batteries | 10 MW · 20 MWh | 2025 | – |
Questions
Carris Storage I, answered
How much can Carris Storage I store and deliver?
Carris Storage I can deliver up to 10 MW and hold 20 MWh of energy, from one battery or storage system. Its net energy in 2025 was -1.1 GWh: a storage plant uses more energy charging than it returns, so the figure is usually negative.
Where is Carris Storage I?
Carris Storage I is in Riverside County, California, at about 33.808°, -116.494°. It is one of 121 power plants of 1 MW or more in the county. The average electricity customer in Riverside County goes 5.0 hours a year without power, the 37th most of 56 counties in California. The county's page has the full outage record.
Who operates Carris Storage I?
It is operated by Hecate Grid Carris Storage 1 LLC (EIA sector: IPP Non-CHP), and it feeds the California ISO.
When did Carris Storage I open?
Its oldest generator still running came online in 2025.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Methodology.