Geothermal power plant · Inyo, CA

Coso Energy Developers

Coso Energy Developers is a 90 MW geothermal power plant in Inyo County, California, operated by Coso Operating Co LLC. Its oldest generator still running came online in 1988. In 2025 it generated 235 GWh, about what 40,000 average California homes use in a year.

Capacity90 MWNameplate, September 2026
Generated235 GWhIn 2025
Capacity factor30%Share of the most it could make, 2025
Generators3Oldest from 1988

Coso Energy Developers in context

Among the 157 other-fuel plants in California in the EIA's inventory, it is the 11th largest, about 1.9% of the state's 4.9 GW of other-fuel capacity.

Inyo County has 19 power plants of 1 MW or more with 465 MW in all; Coso Energy Developers is 19% of that and the 3rd largest of 3 geothermal plants there.

Its capacity factor of 30% in 2025 is higher than the 25% typical for geothermal plants across the US.

The average electricity customer in Inyo County goes 13 hours a year without power, the 24th most of 56 counties in California. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

010020030040020182019202020212022202320242025GWh 235
01002003004002019202120232025235

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Coso Energy Developers (outlined) and other plants in Inyo County, shaded. 36.002, -117.789.

Plant facts

Operator
Coso Operating Co LLC
Sector
IPP Non-CHP
Grid operator
CISO
County
Inyo County, CA
EIA plant ID
10875
Where California's power comes from → California power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
GEN7 Geothermal 30 MW 1988 –
GEN8 Geothermal 30 MW 1988 –
GEN9 Geothermal 30 MW 1989 –

Questions

Coso Energy Developers, answered

How much power does Coso Energy Developers produce?

Coso Energy Developers has 90 MW of capacity from 3 generators. In 2025 it generated 235 GWh, 30% of the most it could have made running flat out all year (its capacity factor).

How many homes does Coso Energy Developers power?

Its 2025 output of 235 GWh equals the yearly electricity use of about 40,000 average California homes (494 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Coso Energy Developers?

Coso Energy Developers is in Inyo County, California, at about 36.002°, -117.789°. It is one of 19 power plants of 1 MW or more in the county. The average electricity customer in Inyo County goes 13 hours a year without power, the 24th most of 56 counties in California. The county's page has the full outage record.

Who operates Coso Energy Developers?

It is operated by Coso Operating Co LLC (EIA sector: IPP Non-CHP), and it feeds the California ISO.

When did Coso Energy Developers open?

Its oldest generator still running came online in 1988.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average California home's 494 kWh a month in 2025. Methodology.