Storage power plant · Inyo, CA
Mordor ES1
Mordor ES1 is a 25 MW storage power plant in Inyo County, California, operated by Mordor ES1 LLC. Its oldest generator still running came online in 2025.
Mordor ES1 in context
Among the 156 storage plants in California in the EIA's inventory, it is the 86th largest, about 0.2% of the state's 13 GW of storage capacity.
Inyo County has 19 power plants of 1 MW or more with 465 MW in all; Mordor ES1 is 5% of that and the 2nd largest of 3 storage plants there.
The average electricity customer in Inyo County goes 13 hours a year without power, the 24th most of 56 counties in California. The county's page has the full outage record.
Where it is
Mordor ES1 (outlined) and other plants in Inyo County, shaded. 36.009, -117.814.
Plant facts
- Operator
- Mordor ES1 LLC
- Sector
- IPP Non-CHP
- Grid operator
- CISO
- County
- Inyo County, CA
- EIA plant ID
- 67828
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| MES1 | Batteries | 25 MW · 100 MWh | 2025 | – |
Nearby
Other plants in Inyo County
Questions
Mordor ES1, answered
How much can Mordor ES1 store and deliver?
Mordor ES1 can deliver up to 25 MW and hold 100 MWh of energy, from one battery or storage system. Its net energy in 2025 was -2.7 GWh: a storage plant uses more energy charging than it returns, so the figure is usually negative.
Where is Mordor ES1?
Mordor ES1 is in Inyo County, California, at about 36.009°, -117.814°. It is one of 19 power plants of 1 MW or more in the county. The average electricity customer in Inyo County goes 13 hours a year without power, the 24th most of 56 counties in California. The county's page has the full outage record.
Who operates Mordor ES1?
It is operated by Mordor ES1 LLC (EIA sector: IPP Non-CHP), and it feeds the California ISO.
When did Mordor ES1 open?
Its oldest generator still running came online in 2025.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Methodology.