Solar power plant · Iron, UT
Cove Mountain Solar 2
Cove Mountain Solar 2 is a 122 MW solar power plant in Iron County, Utah, operated by Cove Mountain Solar 2 LLC. Its oldest generator still running came online in 2020. In 2025 it generated 321 GWh, about what 35,000 average Utah homes use in a year.
Cove Mountain Solar 2 in context
Among the 56 solar plants in Utah in the EIA's inventory, it is the 4th largest, about 4.0% of the state's 3.0 GW of solar capacity.
Iron County has 21 power plants of 1 MW or more with 1.1 GW in all; Cove Mountain Solar 2 is 11% of that and the 2nd largest of 18 solar plants there.
Its capacity factor of 30% in 2025 is higher than the 20% typical for solar plants across the US.
The average electricity customer in Iron County goes 3.8 hours a year without power, the 9th most of 23 counties in Utah. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Cove Mountain Solar 2 (outlined) and other plants in Iron County, shaded. 37.639, -113.637.
Plant facts
- Operator
- Cove Mountain Solar 2 LLC
- Sector
- IPP Non-CHP
- Grid operator
- PACE
- County
- Iron County, UT
- EIA plant ID
- 62470
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| GEN01 | Solar Photovoltaic | 122 MW | 2020 | – |
Questions
Cove Mountain Solar 2, answered
How much power does Cove Mountain Solar 2 produce?
Cove Mountain Solar 2 has 122 MW of capacity from one generator. In 2025 it generated 321 GWh, 30% of the most it could have made running flat out all year (its capacity factor).
How many homes does Cove Mountain Solar 2 power?
Its 2025 output of 321 GWh equals the yearly electricity use of about 35,000 average Utah homes (761 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Cove Mountain Solar 2?
Cove Mountain Solar 2 is in Iron County, Utah, at about 37.639°, -113.637°. It is one of 21 power plants of 1 MW or more in the county. The average electricity customer in Iron County goes 3.8 hours a year without power, the 9th most of 23 counties in Utah. The county's page has the full outage record.
Who operates Cove Mountain Solar 2?
It is operated by Cove Mountain Solar 2 LLC (EIA sector: IPP Non-CHP), and it feeds PacifiCorp East.
When did Cove Mountain Solar 2 open?
Its oldest generator still running came online in 2020.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2020–2025). Homes equivalent uses the average Utah home's 761 kWh a month in 2025. Methodology.