Storage power plant · Iron, UT

Iron Springs BESS

Iron Springs BESS is a 80 MW storage power plant in Iron County, Utah, operated by Iron Springs BESS, LLC. Its oldest generator still running came online in 2026.

Capacity80 MWNameplate, September 2026
Net energy–Not reported
Capacity factor–Not a full year of data
Generators1Oldest from 2026

Iron Springs BESS in context

Among the 7 storage plants in Utah in the EIA's inventory, it is the 4th largest, about 5.4% of the state's 1.5 GW of storage capacity.

Iron County has 21 power plants of 1 MW or more with 1.1 GW in all; Iron Springs BESS is 7% of that and the largest of 3 storage plants there.

The average electricity customer in Iron County goes 3.8 hours a year without power, the 9th most of 23 counties in Utah. The county's page has the full outage record.

Where it is

Iron Springs BESS (outlined) and other plants in Iron County, shaded. 37.729, -113.150.

Plant facts

Operator
Iron Springs BESS, LLC
Sector
IPP Non-CHP
Grid operator
PACE
County
Iron County, UT
EIA plant ID
69041
Where Utah's power comes from → Utah power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
ISBA Batteries 80 MW · 80 MWh 2026 –

Questions

Iron Springs BESS, answered

How much can Iron Springs BESS store and deliver?

Iron Springs BESS can deliver up to 80 MW and hold 80 MWh of energy, from one battery or storage system.

Where is Iron Springs BESS?

Iron Springs BESS is in Iron County, Utah, at about 37.729°, -113.150°. It is one of 21 power plants of 1 MW or more in the county. The average electricity customer in Iron County goes 3.8 hours a year without power, the 9th most of 23 counties in Utah. The county's page has the full outage record.

Who operates Iron Springs BESS?

It is operated by Iron Springs BESS, LLC (EIA sector: IPP Non-CHP), and it feeds PacifiCorp East.

When did Iron Springs BESS open?

Its oldest generator still running came online in 2026.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Methodology.