Natural gas power plant · Kern, CA
Cymric 36W Cogen
Cymric 36W Cogen is a 12 MW natural gas power plant in Kern County, California, operated by Chevron USA Inc. Its oldest generator still running came online in 1982. In 2025 it generated 53 GWh, about what 9,000 average California homes use in a year.
Cymric 36W Cogen in context
Among the 304 natural gas plants in California in the EIA's inventory, it is the 184th largest, about 0.0% of the state's 41 GW of natural gas capacity.
Kern County has 268 power plants of 1 MW or more with 19 GW in all; Cymric 36W Cogen is 0% of that and the 26th largest of 36 natural gas plants there.
Its capacity factor of 49% in 2025 is higher than the 23% typical for natural gas plants across the US.
The average electricity customer in Kern County goes 4.3 hours a year without power, the 43rd most of 56 counties in California. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Cymric 36W Cogen (outlined) and other plants in Kern County, shaded. 35.363, -119.676.
Plant facts
- Operator
- Chevron USA Inc
- Sector
- Industrial CHP
- Grid operator
- CISO
- County
- Kern County, CA
- EIA plant ID
- 52104
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| GEN1 | Natural Gas Fired Combustion Turbine | 3.1 MW | 1982 | – |
| GEN2 | Natural Gas Fired Combustion Turbine | 3.1 MW | 1982 | – |
| GEN3 | Natural Gas Fired Combustion Turbine | 3.1 MW | 1982 | – |
| GEN4 | Natural Gas Fired Combustion Turbine | 3.1 MW | 1982 | – |
Nearby
Other plants in Kern County
Questions
Cymric 36W Cogen, answered
How much power does Cymric 36W Cogen produce?
Cymric 36W Cogen has 12 MW of capacity from 4 generators. In 2025 it generated 53 GWh, 49% of the most it could have made running flat out all year (its capacity factor).
How many homes does Cymric 36W Cogen power?
Its 2025 output of 53 GWh equals the yearly electricity use of about 9,000 average California homes (494 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Cymric 36W Cogen?
Cymric 36W Cogen is in Kern County, California, at about 35.363°, -119.676°. It is one of 268 power plants of 1 MW or more in the county. The average electricity customer in Kern County goes 4.3 hours a year without power, the 43rd most of 56 counties in California. The county's page has the full outage record.
Who operates Cymric 36W Cogen?
It is operated by Chevron USA Inc (EIA sector: Industrial CHP), and it feeds the California ISO.
When did Cymric 36W Cogen open?
Its oldest generator still running came online in 1982.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average California home's 494 kWh a month in 2025. Methodology.