Solar power plant · Riverside, CA

Desert Sunlight 300, LLC

Desert Sunlight 300, LLC is a 314 MW solar power plant in Riverside County, California, operated by NextEra Energy Desert Sunlight 300, LLC. Its oldest generator still running came online in 2013. In 2025 it generated 620 GWh, about what 105,000 average California homes use in a year.

Capacity314 MWNameplate, September 2026
Generated620 GWhIn 2025
Capacity factor23%Share of the most it could make, 2025
Generators11Oldest from 2013

Desert Sunlight 300, LLC in context

Among the 967 solar plants in California in the EIA's inventory, it is the 20th largest, about 1.0% of the state's 32 GW of solar capacity.

Riverside County has 121 power plants of 1 MW or more with 11 GW in all; Desert Sunlight 300, LLC is 3% of that and the 8th largest of 70 solar plants there.

Its capacity factor of 23% in 2025 is close to the 20% typical for solar plants across the US.

The average electricity customer in Riverside County goes 5.0 hours a year without power, the 37th most of 56 counties in California. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

020040060080020182019202020212022202320242025GWh 620
02004006008002019202120232025620

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Desert Sunlight 300, LLC (outlined) and other plants in Riverside County, shaded. 33.823, -115.394.

Plant facts

Operator
NextEra Energy Desert Sunlight 300, LLC
Sector
IPP Non-CHP
Grid operator
CISO
County
Riverside County, CA
EIA plant ID
57993
Where California's power comes from → California power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
DSL1 Solar Photovoltaic 40 MW 2013 –
DSL2 Solar Photovoltaic 40 MW 2013 –
DSL3 Solar Photovoltaic 40 MW 2013 –
DSL10 Solar Photovoltaic 30 MW 2013 –
DSL4 Solar Photovoltaic 30 MW 2013 –
DSL5 Solar Photovoltaic 25 MW 2014 –
DSL6 Solar Photovoltaic 25 MW 2014 –
DSL9 Solar Photovoltaic 23 MW 2014 –
DSL11 Solar Photovoltaic 20 MW 2013 –
DSL7 Solar Photovoltaic 20 MW 2014 –
DSL8 Solar Photovoltaic 19 MW 2014 –

Questions

Desert Sunlight 300, LLC, answered

How much power does Desert Sunlight 300, LLC produce?

Desert Sunlight 300, LLC has 314 MW of capacity from 11 generators. In 2025 it generated 620 GWh, 23% of the most it could have made running flat out all year (its capacity factor).

How many homes does Desert Sunlight 300, LLC power?

Its 2025 output of 620 GWh equals the yearly electricity use of about 105,000 average California homes (494 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Desert Sunlight 300, LLC?

Desert Sunlight 300, LLC is in Riverside County, California, at about 33.823°, -115.394°. It is one of 121 power plants of 1 MW or more in the county. The average electricity customer in Riverside County goes 5.0 hours a year without power, the 37th most of 56 counties in California. The county's page has the full outage record.

Who operates Desert Sunlight 300, LLC?

It is operated by NextEra Energy Desert Sunlight 300, LLC (EIA sector: IPP Non-CHP), and it feeds the California ISO.

When did Desert Sunlight 300, LLC open?

Its oldest generator still running came online in 2013.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average California home's 494 kWh a month in 2025. Methodology.