Solar power plant · Pecos, TX
East Pecos Solar
East Pecos Solar is a 119 MW solar power plant in Pecos County, Texas, operated by Southern Power Co. Its oldest generator still running came online in 2017. In 2025 it generated 219 GWh, about what 16,000 average Texas homes use in a year.
East Pecos Solar in context
Among the 250 solar plants in Texas in the EIA's inventory, it is the 132nd largest, about 0.3% of the state's 37 GW of solar capacity.
Pecos County has 31 power plants of 1 MW or more with 3.7 GW in all; East Pecos Solar is 3% of that and the 9th largest of 13 solar plants there.
Its capacity factor of 21% in 2025 is close to the 20% typical for solar plants across the US.
The average electricity customer in Pecos County goes 8.6 hours a year without power, the 132nd most of 240 counties in Texas. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
East Pecos Solar (outlined) and other plants in Pecos County, shaded. 31.001, -102.282.
Plant facts
- Operator
- Southern Power Co
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Pecos County, TX
- EIA plant ID
- 60436
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Solar Photovoltaic | 119 MW | 2017 | – |
Questions
East Pecos Solar, answered
How much power does East Pecos Solar produce?
East Pecos Solar has 119 MW of capacity from one generator. In 2025 it generated 219 GWh, 21% of the most it could have made running flat out all year (its capacity factor).
How many homes does East Pecos Solar power?
Its 2025 output of 219 GWh equals the yearly electricity use of about 16,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is East Pecos Solar?
East Pecos Solar is in Pecos County, Texas, at about 31.001°, -102.282°. It is one of 31 power plants of 1 MW or more in the county. The average electricity customer in Pecos County goes 8.6 hours a year without power, the 132nd most of 240 counties in Texas. The county's page has the full outage record.
Who operates East Pecos Solar?
It is operated by Southern Power Co (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did East Pecos Solar open?
Its oldest generator still running came online in 2017.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.